Inspection Status: Partial Pass
Inspection History: COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in.
Permit Number - T21CM05003
Inspection Description - COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in.
Inspection Status - Partial Pass
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/12/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Partial Pass | Building progress only. | |
06/10/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Partial Pass | Inspection is for rebar footings and patio walls. OK to place concrete in progress areas. | |
07/01/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Partial Pass | This inspection is for patio walls at 0” - 48”. Ok to,place grout in progress areas | |
07/10/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Partial Pass | 10/5/23: Electrical intermediate passed. 7/10/24:This inspection is for patio walls at 48"- 96”. Ok to,place grout in progress areas |
|
07/16/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | OK to insulate and sheet rock. | |
07/19/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Partial Pass | 10/5/23: Electrical intermediate passed. 7/10/24:This inspection is for patio walls at 48"- 96”. Ok to,place grout in progress areas 7/19/24: this inspection is for patio walls at 96"- 144". Ok to place grout at progress areas |
|
07/24/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Partial Pass | Masonry pre-grout of CMU walls at topped-out at 22feet. Ok to place grout in progress areas. | |
08/05/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Partial Pass | This inspection is for South Masonry wall at 22’, topped-out. Ok to grout progress areas. | |
10/05/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Partial Pass | 10/5/23: Electrical intermediate passed. |