Permit: T21CM03856
Permit Details
Status:
Issued
Type:
Residential Building - One or Two Family
Address:
1231 W KLEINDALE RD
Address NEW:
1231 W KLEINDALE RD
Apply Date:
05/06/2021
Applicant:
Ivonne Pereyra
Description:
SFR Renovation and Addition
Permit Reviews
Permit Number - T21CM03856
Permit Status: Issued
Permit Description: SFR Renovation and Addition
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/06/2021 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 06/04/2021 | COMPLETED |
| 09/23/2021 | RESUBMITTAL | 10/06/2021 | COMPLETED |
| 10/29/2021 | RESUBMITTAL | 11/04/2021 | COMPLETED |
Outstanding Inspections
Permit Status: Issued
Permit Number: T21CM03856
Permite Description: SFR Renovation and Addition
Total Outstanding Inspections - 4
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2022 | COT - RSBU - Preslab | N/A | Not Ready | |
| 10/27/2022 | RSBU - Building Final | N/A | Not Ready | |
| 10/27/2022 | COT - RSEL - Electrical Final | N/A | Not Ready | |
| 10/27/2022 | RSME - Mechanical Progress | N/A | Not Ready |
Completed Inspections
Permit Status: Issued
Permit Number: T21CM03856
Permit Description: SFR Renovation and Addition
Total Completed Inspections - 6
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/26/2021 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 11/26/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved} | |
| 04/29/2022 | COT - RSBU - Roof Nailing | Passed | {Activity date: 04/29/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} ; {Activity date: 04/25/2022; Status: Not ready for Inspection; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Not ready} ; {Activity date: 04/22/2022; Status: Not ready for Inspection; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Not inspected} | |
| 04/29/2022 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | {Activity date: 04/29/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} ; {Activity date: 04/25/2022; Status: Not ready for Inspection; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Not ready} ; {Activity date: 04/22/2022; Status: Not ready for Inspection; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Not ready shear not nailed, no plans on site inspection canceled} | |
| 05/31/2022 | RSEL - Electrical Progress | Passed | {Activity date: 05/31/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} | |
| 06/03/2022 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 06/03/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - approved} | |
| 06/03/2022 | COT - LCBU - Framing | Passed | {Activity date: 06/03/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - approved} ; {Activity date: 05/31/2022; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Partial. Missing rat runs on trusses, (a).} ; {Activity date: 04/25/2022; Status: Denied; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Denied Plans do not reflect work as accomplished, please revise plan showing as built, 4x4s where required and pony wall on tot of block wall and approved truss design as built} ; {Activity date: 04/22/2022; Status: Not ready for Inspection; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Not inspected please call with intermediate inspections } |