Permit: T21CM03681
Permit Details
Apply Date:
05/03/2021
Applicant:
Description:
New electric vehicle sales and service facility.
Permit Reviews
Permit Number - T21CM03681
Permit Status: Issued
Permit Description: New electric vehicle sales and service facility.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/03/2021 | 3RD PARTY REVIEW - COMMERCIAL | 07/13/2021 | COMPLETED |
| 08/30/2021 | REVISION - - 1ST | 09/20/2021 | COMPLETED |
Conditions
Permit Number - T21CM03681
Permit Status: Issued
Permit Description: New electric vehicle sales and service facility.
| Date | Description | Comments |
|---|---|---|
| 07/08/2021 | SPECIAL INSPECTION FOR CONCRETE IS REQUIRED.. | |
| 07/08/2021 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 07/08/2021 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. | |
| 09/21/2021 | This building permit approval is without public sewer connection review or approval. It is strictly the responsibility of the owner and/or person doing the work to ensure that the appropriate review and approval to connect is obtained from Regional Wastewater Reclamation Department (RWRD) wastewater provider or Pima County DEQ approval of/and alternative disposal system. It is required that owner and/or person doing the work solicit all requisite approvals from the wastewater provider prior to obtaining this building construction permit. RWRD connection information is available at www.pima.gov/wwm/developer.htm | |
| 07/08/2021 | SPECIAL INSPECTION IS REQUIRED FOR SOILS | |
| 07/08/2021 | SPECIAL INSPECTION IS REQUIRED FOR FABRICATORS | |
| 07/08/2021 | SPECIAL INSPECTION IS REQUIRED FOR STEEL | |
| 07/08/2021 | SPECIAL INSPECTION IS REQUIRED FOR COLD FORMED STEEL | |
| 07/08/2021 | SPECIAL INSPECTION IS REQUIRED FOR MASONRY | |
| 07/19/2022 | SPECIAL INSPECTION IS REQUIRED FOR WATER CHLORINATION REPORT. | |
| 09/21/2021 | PIMA COUNTY WASTEWATER SIGN OFF REQUIRED PRIOR TO ISSUANCE OF FINAL STATUS. |
Outstanding Inspections
Permit Status: Issued
Permit Number: T21CM03681
Permite Description: New electric vehicle sales and service facility.
Total Outstanding Inspections - 8
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/17/2022 | COT - LCPL - Medical Gas Preconstruction Mtg | N/A | Canceled | {Activity date: 02/17/2022; Status: Not Applicable; Inspector: DQUINN; Comment: Entered by RSALDAT1 - TELSL DEALERSHIP} |
| 06/03/2022 | COT - LCBU - Masonry Pregrout | N/A | Canceled | {Activity date: 06/03/2022; Status: Not Applicable; Inspector: aquiroz; Comment: Entered by AQUIROZ - } |
| 06/22/2022 | COT - LCEL - Service Relocation | N/A | Canceled | {Activity date: 06/22/2022; Status: Not Applicable; Inspector: DQUINN; Comment: Entered by VVERA1 - na No relo. All new} ; {Activity date: 06/17/2022; Status: Not ready for Inspection; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Nr} |
| 08/10/2022 | COT - LCPL - Backwater Valve | N/A | Canceled | {Activity date: 08/10/2022; Status: Not Applicable; Inspector: RSHERRY; Comment: Entered by RSHERRY1 - NO BACKWATER VALVE REQUIRED} ; {Activity date: 07/18/2022; Status: Not ready for Inspection; Inspector: DQUINN; Comment: Entered by VVERA1 - nr Plumbing sub being contacted for test. } ; {Activity date: 07/15/2022; Status: Partial Approval; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - PA} ; {Activity date: 07/14/2022; Status: Not ready for Inspection; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Not ready. Could not locate job site. No contact phone number.} ; {Activity date: 07/13/2022; Status: Not ready for Inspection; Inspector: TGAUSP; Comment: Entered by VVERA1 - NR, cancelled by Contractor } |
| 11/07/2022 | COT - LCBU - Building Final | N/A | Canceled | Inspection Canceled |
| 11/07/2022 | ENGR Engineering Final | N/A | Canceled | Inspection Canceled |
| 07/14/2023 | PDSD Building Division Pre-Construction Meeting | N/A | Canceled | |
| 01/23/2023 | COT - HCBU - Building Final | N/A | Not Ready | Unable to locate building; post address visible from street. |
Completed Inspections
Permit Status: Issued
Permit Number: T21CM03681
Permit Description: New electric vehicle sales and service facility.
Total Completed Inspections - 30
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/24/2021 | COT - LCBU - Stem Wall/Retaining Wall | Passed | {Activity date: 09/24/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by VVERA1 - Ap} | |
| 10/21/2021 | COT - LCBU - Preslab | Passed | {Activity date: 10/21/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap} ; {Activity date: 09/07/2021; Status: Denied; Inspector: RELEFANTE; Comment: Entered by RSALDAT1 - DE( did not have the underground plumbing filled up for test)} | |
| 01/19/2022 | COT - LCEL - Electrical Intermediate | Passed | {Activity date: 01/19/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap All in wall electric ok to rock.} |
|
| 01/20/2022 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 01/20/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by RSALDAT1 - Ap } ; {Activity date: 01/19/2022; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - RI canceled} |
|
| 01/20/2022 | COT - LCPL - Plumbing Above Ceiling | Passed | {Activity date: 01/20/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by RSALDAT1 - Ap } ; {Activity date: 01/19/2022; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - RI canceled} |
|
| 01/26/2022 | COT - LCBU - Framing | Passed | {Activity date: 01/26/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by VVERA1 - Approved} ; {Activity date: 12/29/2021; Status: Not ready for Inspection; Inspector: DQUINN; Comment: Entered by VVERA1 - nr Need in wall 35s before wall frame inspection. } |
|
| 01/27/2022 | COT - LCBU - Exterior Clips/Sheathing | Passed | {Activity date: 01/27/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved, okay to cover } ; {Activity date: 12/22/2021; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by VVERA1 - Partial. Metal shearwalls on the southeast and northeast side of building.} ; {Activity date: 12/09/2021; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by VVERA1 - pa Exterior metal shearwalls ok to cover on north, west and west end of south wall. Interior horizontal strapping on these walls ok. Top of parapet perpendicular ties ok.} ; {Activity date: 12/02/2021; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by VVERA1 - Partial. Steel sheer wall on west side of building.} |
|
| 02/01/2022 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 02/01/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by VVERA1 - Ap} ; {Activity date: 12/28/2021; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by NGARCIA3 - pa South and east side dense glass ok to cover.} ; {Activity date: 12/17/2021; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by NGARCIA3 - pa Dense glass sub wall, on north side, ok to cover.} |
|
| 02/17/2022 | COT - LCBU - Sustainability | Passed | {Activity date: 02/17/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by RSALDAT1 - } | |
| 02/17/2022 | COT - LCEL - Electrical Above Ceiling | Passed | {Activity date: 02/17/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by RSALDAT1 - } ; {Activity date: 02/02/2022; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Pa All above conduits in place. Need drop tile lights and supports and labeled j boxes to sign off 2036.} ; {Activity date: 01/19/2022; Status: Not ready for Inspection; Inspector: DQUINN; Comment: Entered by NGARCIA3 - nr} |
|
| 02/17/2022 | COT - LCBU - Roof Nailing | Passed | {Activity date: 02/17/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by RSALDAT1 - } ; {Activity date: 12/17/2021; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by NGARCIA3 - pa Steel sub deck of roof ok to cover.} |
|
| 02/17/2022 | COT - LCPL - Sewer | Passed | {Activity date: 02/17/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by RSALDAT1 - } | |
| 03/03/2022 | COT - LCBU - Building Above Ceiling | Passed | {Activity date: 03/03/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap} | |
| 03/03/2022 | COT - LCME - Mechanical Above Ceiling | Passed | {Activity date: 03/03/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap} | |
| 03/03/2022 | COT - LCME - Mechanical Intermediate | Passed | {Activity date: 03/03/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap} | |
| 04/13/2022 | COT - LCEL - Electrical Underground | Passed | {Activity date: 04/13/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by VVERA1 - Ap All site underground complete} ; {Activity date: 02/07/2022; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by VVERA1 - Pa Under conduits ok to backfill for all remaining light poles.} ; {Activity date: 02/02/2022; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by NGARCIA3 - pa Trench from building to monument ok to backfill. } ; {Activity date: 01/31/2022; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by RSALDAT1 - pa From light pole #4 to #5, 100’ towards #6 - ok to backfill.} ; {Activity date: 01/26/2022; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by VVERA1 - Partial. Secondaries from driveway to transformer are complete.} ; {Activity date: 01/19/2022; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by NGARCIA3 - pa Conduits to light poles and charging stations ok to backfill. } ; {Activity date: 01/07/2022; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by VVERA1 - pa Secondaries from building to driveway ok to backfill. Secondaries yet to be completed from driveway to TEP trans. Conduits from building panels, adjacent to building running south to SW corner, for car chargers, ok to backfill.} ; {Activity date: 09/23/2021; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by NGARCIA3 - pa Secondaries on east side, under stem and up to service location on Interior, ok. Secondary runs to trans nr.} ; {Activity date: 09/15/2021; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by NGARCIA3 - pa Floor box and monument conduits ok. All west side exterior conduits ok to backfill. East side nr.} ; {Activity date: 09/13/2021; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by NGARCIA3 - pa 1-3” from W wall to mid N wall. 2-3” and 2- 1” from SW corner to mid N wall. 1-2 1/2” from E wall to mid N wall. 1-3” and 2-2 1/2” from IT room to mid N wall. All above conduits ok to backfill. } ; {Activity date: 09/07/2021; Status: Partial Approval; Inspector: RELEFANTE; Comment: Entered by RSALDAT1 - (conduit located in the northwest wall footing this is for the sleeve)} |
|
| 04/28/2022 | COT - LCPL - Rough Soil | Passed | {Activity date: 04/28/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap All underground water and drainage complete for this site, including fire water. } ; {Activity date: 10/07/2021; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by RSALDAT1 - pa all interior ok. Still exterior to complete.} ; {Activity date: 09/07/2021; Status: Denied; Inspector: RELEFANTE; Comment: Entered by RSALDAT1 - DE( did not have the underground plumbing filled up for test)} |
|
| 05/06/2022 | COT - LCEL - Grounding/Bonding | Passed | {Activity date: 05/06/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap Ufers complete in TS1, TS2, and TSC} ; {Activity date: 02/16/2022; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by NGARCIA3 - pa Light poles # 6 and 7 ok to pour } ; {Activity date: 01/14/2022; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by NGARCIA3 - pa 4 light pole footings ok to pour.} |
|
| 05/20/2022 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 05/20/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - CODE ECO 5081 N Oracle rd. } |
|
| 06/17/2022 | COT - LCBU - Building Progress | Passed | {Activity date: 06/17/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap} | |
| 06/22/2022 | COT - LCEL - Electrical Final | Passed | {Activity date: 06/22/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by VVERA1 - Ap} ; {Activity date: 05/20/2022; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by NGARCIA3 - pa Ok to energize SES and all distribution except TS1, TS2, and TSC. (Waiting for parts to ship. Those components will be locked out when energized) Clear eco for address 5081 N Oracle rd.} ; {Activity date: 05/10/2022; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Not Ready} |
|
| 07/07/2022 | COT - LCME - Mechanical Progress | Passed | {Activity date: 07/07/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap} | |
| 07/15/2022 | COT - LCME - Mechanical Final | Passed | {Activity date: 07/15/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 07/14/2022; Status: Partial Approval; Inspector: RSHERRY; Comment: Entered by RSHERRY1 - REVIEW OF AIR BALANCE REPORT COMPLETED} ; {Activity date: 07/14/2022; Status: Not ready for Inspection; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Not ready. Could not locate job site.} ; {Activity date: 07/07/2022; Status: Not ready for Inspection; Inspector: DQUINN; Comment: Entered by NGARCIA3 - nr Need air balance reviewed and approved by COT} ; {Activity date: 09/21/2021; Status: Prior to Final Inspectn; Inspector: LBOWERS; Comment: Entered by LBOWERS1 - AIR BALANCE REPORT REQUIRED PRIOR TO FINAL INSPECTION} |
|
| 07/15/2022 | COT - LCBU - Excavation/Rebar/Zoning | Passed | {Activity date: 07/15/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 02/16/2022; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by NGARCIA3 - pa} ; {Activity date: 01/14/2022; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by NGARCIA3 - pa } ; {Activity date: 11/24/2021; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by NGARCIA3 - pa 2 pop out footings, on N. and S. of entryway, ok to pour.} ; {Activity date: 09/13/2021; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by NGARCIA3 - pa 31’ of stem, at N end of W wall, ok to pour. W and S retaining walls, from 3 to 6 1/2’ high, ok to pour} ; {Activity date: 09/08/2021; Status: Partial Approval; Inspector: RELEFANTE; Comment: Entered by RSALDAT1 - PA} ; {Activity date: 09/07/2021; Status: Partial Approval; Inspector: RELEFANTE; Comment: Entered by RSALDAT1 - PA( NORTH&WEST RETAINING WALL FOOTINGS APPROVED ONLY, (6) INTERIOR FOOTINGS ONLY)} |
|
| 07/15/2022 | COT - LCEL - Construction Power | Passed | {Activity date: 07/15/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 05/10/2022; Status: Correction Required; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - corrections required, Provide permanent site address & address tag for SES, Torque and mark all terminations in SES, MDP, & XFMRs. Provide Lock out Tag out for incomplete (120/208v) panels due to procurement issues. Submit approved engineered Alternatives for 120/208v panel changes. Construction meeting was scheduled with COT, TEP, & Construction team to discuss all the following. } |
|
| 07/15/2022 | SITE - Zoning Final | Passed | {Activity date: 07/15/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 09/22/2021; Status: Prior to Final Inspectn; Inspector: EHamblin; Comment: Entered by EHAMBLI1 - Zoning inspection to verify work in ADOT ROW has been completed. Contact Elisa Hamblin or James Gomez at ADOT jgomes@azdot.gov} | |
| 07/15/2022 | COT - FCON - Alarm - Final | Passed | {Activity date: 07/15/2022; Status: Approved; Inspector: jfordney; Comment: Entered by JFORDNE1 - } ; {Activity date: 07/14/2022; Status: Not ready for Inspection; Inspector: jfordney; Comment: Entered by JFORDNE1 - } | |
| 07/15/2022 | COT - FCON - Sprinkler - Final | Passed | {Activity date: 07/15/2022; Status: Approved; Inspector: jfordney; Comment: Entered by JFORDNE1 - } ; {Activity date: 07/14/2022; Status: Not ready for Inspection; Inspector: jfordney; Comment: Entered by JFORDNE1 - } ; {Activity date: 06/28/2022; Status: Prior to Final Inspectn; Inspector: wmotto; Comment: Entered by WMOTTO1 - Underground fire line has been buried and not inspected by tucsonfire. Nn pressure test and no visual inspection.} | |
| 07/15/2022 | COT - LCPL - Plumbing Final | Passed | {Activity date: 07/15/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 09/21/2021; Status: Prior to Final Inspectn; Inspector: LBOWERS; Comment: Entered by LBOWERS1 - WATER QUALITY REPORT REQURIED PRIOR TO FINAL INSPECTION} ; {Activity date: 09/21/2021; Status: Prior to Final Inspectn; Inspector: LBOWERS; Comment: Entered by LBOWERS1 - SEWER FEES NEED TO BE PAID BEFORE PLUMBING FINAL} | |
| 09/20/2022 | COT - FCON - Fire - Final | Passed | {Activity date: 09/20/2022; Status: Approved; Inspector: wmotto; Comment: Entered by WMOTTO1 - } ; {Activity date: 07/15/2022; Status: Partial Approval; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - PA} ; {Activity date: 07/15/2022; Status: Partial Approval; Inspector: jfordney; Comment: Entered by JFORDNE1 - OK to obtain TCO Knox box Address Identification Fire extinguisher identification} ; {Activity date: 07/07/2022; Status: Denied; Inspector: wmotto; Comment: Entered by WMOTTO1 - 1. underground pressure test was done and dropped 25 lbs in two hours. There appears to be a leak in the underground fire line that was not inspected by tucson fire.} ; {Activity date: 06/28/2022; Status: Prior to Final Inspectn; Inspector: wmotto; Comment: Entered by WMOTTO1 - Underground fire line has been buried and not inspected by tucsonfire. Nn pressure test and no visual inspection.} |