Permit Details

Status:
Issued
Type:
Commercial Building
Apply Date:
04/19/2021
Applicant:
Bryon Peel-Davis
Description:
Instrumentation/control upgrade including new vault and control building.CDRC indicated that no Spe

Permit Reviews

Permit Number - T21CM03291
Permit Status: Issued
Permit Description: Instrumentation/control upgrade including new vault and control building.CDRC indicated that no Spe
Start Date Submittal Complete Date Status  
04/19/2021 COMMERCIAL - TI 06/03/2021 COMPLETED Review Details
06/03/2021 COMMERCIAL - TI 07/19/2021 COMPLETED Review Details
08/16/2021 RESUBMITTAL 08/26/2021 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T21CM03291
Permit Status: Issued
Permit Description: Instrumentation/control upgrade including new vault and control building.CDRC indicated that no Spe
Total Outstanding Activity Conditions - 6
Date Name
05/04/2021 SPECIAL INSPECTION FORMS AND REPORTS REQUIRED PRIOR TO ISSUANCE OF A CERTIFICATE OF OCCUPANCY.
05/04/2021 SPECIAL INSPECTION FOR CONCRETE IS REQUIRED..
05/04/2021 SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED.
05/04/2021 SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED.
06/15/2021 SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED.
06/15/2021 SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED.

Outstanding Inspections

Permit Status: Issued
Permit Number: T21CM03291
Permite Description: Instrumentation/control upgrade including new vault and control building.CDRC indicated that no Spe
Total Outstanding Inspections - 7
Last Inspection Date Description Inspector Results Comments
04/05/2022 COT - LCEL - Temporary Service N/A Canceled {Activity date: 04/05/2022; Status: Not Applicable; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - not applicable
}
11/04/2022 COT - LCBU - Building Final N/A Canceled Inspection Canceled
11/04/2022 COT - LCME - Mechanical Final N/A Canceled Inspection Canceled
11/04/2022 COT - LCEL - Outdoor Lighting N/A Canceled Inspection Canceled
11/04/2022 COT - FCON - Fire - Final N/A Canceled Inspection Canceled
11/04/2022 COT - LCME - Mechanical Intermediate N/A Canceled Inspection Canceled
11/07/2022 COT - LCEL - Electrical Underground N/A Canceled Inspection Canceled

Completed Inspections

Permit Status: Issued
Permit Number: T21CM03291
Permit Description: Instrumentation/control upgrade including new vault and control building.CDRC indicated that no Spe
Total Completed Inspections - 13
Date Description Inspector Results Comments
01/13/2022 COT - LCEL - Grounding/Bonding Passed {Activity date: 01/13/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved, EGC connections to ground ring for control room equipment complete.
} ; {Activity date: 01/03/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved, 3-O copper ring and grid}
01/25/2022 COT - LCBU - Excavation/Rebar/Zoning Passed {Activity date: 01/25/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved, Control room slab re enforcement installed and ok for concrete placement.} ; {Activity date: 01/13/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - PARTIAL, Inspection for Control Room footings F1, OK for concrete placement. Note: required special inspection report for Masonry Control Joints that were missing, and spoil clean out prior to concrete.}
01/25/2022 COT - LCBU - Preslab Passed {Activity date: 01/25/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved, Control room slab ok for concrete placement.} ; {Activity date: 01/13/2022; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - NOT READY.
}
02/02/2022 PDSD Building Division - TEP PM Clearance Passed {Activity date: 02/02/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - CODE ECO}
02/02/2022 COT - LCEL - Construction Power Passed {Activity date: 02/02/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved, clear TEP ECO}
04/05/2022 COT - LCBU - Stem Wall/Retaining Wall Passed {Activity date: 04/05/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved}
04/05/2022 COT - LCEL - Electrical Progress Passed {Activity date: 04/05/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved}
04/05/2022 COT - LCEL - Electrical Intermediate Passed {Activity date: 04/05/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 03/11/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, Inspection of Booster Control panels, Feeders, and PLC Connections-in Control room ok to proceed.

}
04/05/2022 COT - LCBU - Framing Passed {Activity date: 04/05/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved}
04/05/2022 COT - LCEL - Electrical Above Ceiling Passed {Activity date: 04/05/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved}
04/05/2022 COT - LCBU - Building Progress Passed {Activity date: 04/05/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved}
04/05/2022 COT - LCBU - Masonry Pregrout Passed {Activity date: 04/05/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved}
11/04/2022 COT - LCEL - Electrical Final Passed Approved, pending all other final inspections