Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T21CM02719
Permit Details
Apply Date:
03/26/2021
Applicant:
Solon Corporation
Description:
Construction of Solar Parking Canopies.
Contractors:
- Solon Corporation
- SOLON CORPORATION ***APA***
Permit Reviews
Permit Number - T21CM02719
Permit Status: L of c
Permit Description: Construction of Solar Parking Canopies.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/26/2021 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 04/27/2021 | COMPLETED |
05/25/2021 | RESUBMITTAL | 06/09/2021 | COMPLETED |
07/06/2021 | RESUBMITTAL | 07/22/2021 | COMPLETED |
Completed Inspections
Permit Status: L of c
Permit Number: T21CM02719
Permit Description: Construction of Solar Parking Canopies.
Total Completed Inspections - 12
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/25/2021 | ELECTRIC - UFER | DMUNIZ | Approved | Approved, canopy A,B,C,D meet grounding requirements |
08/25/2021 | BUILDING PRE-SLAB | DMUNIZ | Approved | Approved |
08/25/2021 | EXCAVATION/LAYOUT REBAR & ZON | DMUNIZ | Approved | Approved |
09/09/2021 | ELECTRIC - UNDERGROUND | DMUNIZ | Approved | Partial, phase 1 conduits installed and ok to backfill |
10/30/2021 | ELECTRIC - INTERMEDIATE | DMUNIZ1 | Approved | Interconnection of PV Disconnect to Service Entrance Switchgear Approved, Verbal Clearance sent to TEP for RECN @ 9:15AM. |
06/17/2022 | TEP CLEARANCE - PM | DMUNIZ | Approved | CODE DGC |
06/17/2022 | ELECTRIC - FINAL | DMUNIZ | Approved | Approved, clear TEP DGC. |
06/17/2022 | OUTDOOR LIGHTING FINAL | DMUNIZ | Approved | Approved |
06/17/2022 | BUILDING - FINAL | DMUNIZ | Approved | Approved |
06/17/2022 | ELECTRIC - OUTDOOR LIGHTING | DMUNIZ | Approved | Approved |
06/17/2022 | BUILDING - PROGRESS | DMUNIZ | Approved | Approved |
06/17/2022 | FRAMING | DMUNIZ | Approved | Approved |