Permit Details

Status:
C of o
Type:
COMMERCIAL ALTERATION
Address NEW:
910 E SPEEDWAY BL 130
Apply Date:
03/24/2021
Applicant:
Krista Moore
Description:
COFFEE SHOP
Architects:
  • Will Reilly
Contractors:
  • KDC Construction

Permit Reviews

Permit Number - T21CM02677
Permit Status: C of o
Permit Description: COFFEE SHOP
Start Date Submittal Complete Date Status  
03/24/2021 COMMERCIAL - TI 04/23/2021 COMPLETED Review Details
05/14/2021 RESUBMITTAL 10/06/2021 COMPLETED Review Details

Completed Inspections

Permit Status: C of o
Permit Number: T21CM02677
Permit Description: COFFEE SHOP
Total Completed Inspections - 25
Date Description Inspector Results Comments
06/30/2021 ELECTRIC - INTERMEDIATE ESTEVENS Approved
06/30/2021 FRAMING ESTEVENS Approved
07/02/2021 PLUMBING - INTERMEDIATE ESTEVENS Approved
07/14/2021 MECHANICAL - INTERMEDIATE DQUINN Approved Ap
07/14/2021 PLUMBING - ABOVE CEILING DQUINN Approved Ap
Ok to insulate pipes
07/28/2021 ELECTRIC - ABOVE CEILING ESTEVENS Approved Approved.
08/23/2021 TEP CLEARANCE - PM RELEFANTE Approved CODE INCR
08/23/2021 ELECTRIC - SERVICE UPGRADE RELEFANTE Approved AP

Clear INCR
09/09/2021 FIRE - FINAL wmotto1 Approved Approved via facetime.
09/09/2021 FIRE - ALARM FINAL wmotto1 Approved Approved via facetime.
09/09/2021 FIRE SPKLR - FINAL wmotto1 Approved Approved via facetime.
09/10/2021 ELECTRIC - FINAL ESTEVENS Approved Approved.
09/13/2021 PLUMBING - FINAL RSHERRY Approved REVIEW OF WATER DISINFECTION REPORT COMPLETED
09/13/2021 MECHANICAL - FINAL RSHERRY Approved REVIEW OF AIR BALANCE REPORT COMPLETED
10/06/2021 BUILDING - FINAL JG3 Approved All Final inspections have been completed and Health Cetificate verified.
10/06/2021 HEALTH DEPT - FINAL 724-7908 JG3 Approved
10/06/2021 OUTDOOR LIGHTING FINAL JG3 Approved
10/06/2021 ELECTRIC - PROGRESS JG3 Approved Electrical Final has been approved
10/06/2021 ELECTRIC - OUTDOOR LIGHTING JG3 Approved Electrical Final has been approved
10/06/2021 BUILDING - PROGRESS JG3 Approved Building Final has been approved
10/06/2021 SHEET ROCK NAILING JG3 Approved Building Final has been approved
10/06/2021 BUILDING ABOVE CEILING JG3 Approved Building Final has been approved
10/06/2021 PLUMBING - PROGRESS JG3 Approved Plumbing Final has been approved
10/06/2021 MECHANICAL - ABOVE CEILING JG3 Approved Mechanical Final has been approved
10/06/2021 MECHANICAL - PROGRESS JG3 Approved Mechanical Final has been approved