Permit: T21CM02478
Permit Details
Apply Date:
03/18/2021
Applicant:
Description:
Upgrade existing electrical to an 800AMP, 3PH, 120/208V REV1: Upgrade to 600amp, 3PH, 120/208V
Permit Reviews
Permit Number - T21CM02478
Permit Status: Inspections
Permit Description: Upgrade existing electrical to an 800AMP, 3PH, 120/208V REV1: Upgrade to 600amp, 3PH, 120/208V
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/19/2021 | OTHER | 04/16/2021 | COMPLETED |
| 06/23/2021 | RESUBMITTAL | 06/28/2021 | COMPLETED |
| 10/10/2023 | COMMERCIAL PDSD SIMPLE REVIEW v.1 | 10/23/2023 | REQUIRES RESUBMIT |
| 11/02/2023 | COMMERCIAL PDSD SIMPLE REVIEW v.2 | 11/13/2023 | APPROVED |
Outstanding Inspections
Permit Status: Inspections
Permit Number: T21CM02478
Permite Description: Upgrade existing electrical to an 800AMP, 3PH, 120/208V REV1: Upgrade to 600amp, 3PH, 120/208V
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/04/2022 | COT - LCEL - Temporary Service | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - LCEL - Service Upgrade | N/A | Canceled | Inspection Canceled |
Completed Inspections
Permit Status: Inspections
Permit Number: T21CM02478
Permit Description: Upgrade existing electrical to an 800AMP, 3PH, 120/208V REV1: Upgrade to 600amp, 3PH, 120/208V
Total Completed Inspections - 5
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/25/2025 | COT - LCEL - Electrical Underground | Passed | Approved 2 - 4" electrical conduits from CT can to TEP pull box, okay to backfill progress areas | |
| 06/25/2025 | COT - LCEL - Grounding/Bonding | Passed | ||
| 07/23/2025 | COT - LCEL - Electrical Intermediate | Passed | ||
| 07/23/2025 | BULD - Electrical Clearance | Passed | Approved 600A 3-phase service panel upgrade - INCR Clearance to TEP is required for the cutover Pending final |
|
| 09/02/2025 | COT - LCEL - Electrical Final | Passed |