Permit: T21CM01616
Permit Details
Status:
Issued
Type:
Commercial Building
Address:
1038 E FORT LOWELL RD
Address NEW:
1038 E FORT LOWELL RD
Apply Date:
02/23/2021
Applicant:
Description:
installation of a 5.22 kw AC solar structure
Permit Reviews
Permit Number - T21CM01616
Permit Status: Issued
Permit Description: installation of a 5.22 kw AC solar structure
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/23/2021 | COMMERCIAL - TI | 04/09/2021 | COMPLETED |
| 05/13/2022 | RESUBMITTAL | 06/22/2022 | COMPLETED |
| 08/20/2021 | RESUBMITTAL - TI ALL | 09/20/2021 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T21CM01616
Permit Status: Issued
Permit Description: installation of a 5.22 kw AC solar structure
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/25/2021 | FUP T21OT00621 MUST BE PAID BEFORE FINAL INSPECTIONS. |
Completed Inspections
Permit Status: Issued
Permit Number: T21CM01616
Permit Description: installation of a 5.22 kw AC solar structure
Total Completed Inspections - 9
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/26/2022 | COT - LCBU - Excavation/Rebar/Zoning | Passed | {Activity date: 07/26/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - approved} | |
| 07/26/2022 | COT - LCEL - Grounding/Bonding | Passed | {Activity date: 07/26/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - approved} | |
| 08/02/2022 | COT - LCEL - Electrical Underground | Passed | {Activity date: 08/02/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap 3’ conduit run from building to column, ok to backfill.} ; {Activity date: 07/26/2022; Status: Not ready for Inspection; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - not ready} |
|
| 08/22/2022 | COT - LCBU - Building Final | Passed | {Activity date: 08/22/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved} | |
| 08/22/2022 | COT - LCEL - Electrical Intermediate | Passed | {Activity date: 08/22/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved} | |
| 08/22/2022 | COT - LCBU - Framing | Passed | {Activity date: 08/22/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved} | |
| 08/22/2022 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 08/22/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - CODE DGC} | |
| 08/22/2022 | COT - LCEL - Electrical Final | Passed | {Activity date: 08/22/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved, please send DGC Clearance to TEP for the solar meter} | |
| 08/22/2022 | COT - LCBU - Building Progress | Passed | {Activity date: 08/22/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved} |