Permit: T21CM01253
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
2200 N CAMINO PRINCIPAL BLDG 4
Address NEW:
2200 N CAMINO PRINCIPAL BLDG 4
Apply Date:
02/11/2021
Applicant:
Michael Scarbrough
Description:
3 existing building remodels and 1 new building addition to a former abandoned commercial office add
Permit Reviews
Permit Number - T21CM01253
Permit Status: Complete
Permit Description: 3 existing building remodels and 1 new building addition to a former abandoned commercial office add
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/11/2021 | COMMERCIAL - TI | 04/26/2021 | COMPLETED |
| 04/26/2021 | RESUBMITTAL | 05/24/2021 | COMPLETED |
| 05/25/2021 | RESUBMITTAL | 09/20/2021 | COMPLETED |
| 12/27/2022 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/05/2023 | APPROVED |
Outstanding Activity Conditions
Permit Number - T21CM01253
Permit Status: Complete
Permit Description: 3 existing building remodels and 1 new building addition to a former abandoned commercial office add
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 02/11/2021 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T21CM01253
Permite Description: 3 existing building remodels and 1 new building addition to a former abandoned commercial office add
Total Outstanding Inspections - 5
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/09/2022 | COT - LCME - Kitchen Hood | N/A | Not Applicable | NA |
| 12/09/2022 | BULD - Electrical Clearance | N/A | Not Applicable | Already connected. |
| 12/09/2022 | COT - FCON - Sprinkler - Final | N/A | Partial Pass | Fire alarm not installed yet. |
| COT - FCON - Fire - Final | N/A | Not Ready | ||
| 01/10/2023 | COT - LCBU - Building Final | N/A | Partial Pass | Need pool complete, service permanent parts, and elevator complete. Recommend issuing TCO. |
Completed Inspections
Permit Status: Complete
Permit Number: T21CM01253
Permit Description: 3 existing building remodels and 1 new building addition to a former abandoned commercial office add
Total Completed Inspections - 31
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/15/2021 | COT - LCPL - Rough Soil | Passed | {Activity date: 12/15/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
| 12/28/2021 | COT - LCBU - Excavation/Rebar/Zoning | Passed | {Activity date: 12/28/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by RSALDAT1 - AP} | |
| 03/16/2022 | COT - LCEL - Electrical Underground | Passed | {Activity date: 03/16/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} ; {Activity date: 03/03/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - PA. Feeder conduits past pool area.} | |
| 04/25/2022 | COT - LCBU - Roof Nailing | Passed | {Activity date: 04/25/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} | |
| 05/18/2022 | COT - LCBU - Sustainability | Passed | {Activity date: 05/18/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} | |
| 05/25/2022 | COT - LCBU - Framing | Passed | {Activity date: 05/25/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} ; {Activity date: 04/25/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Partial approval for 2nd floor walls and water heater closet } ; {Activity date: 03/03/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - -PA. Deck nailing. Mike} |
|
| 06/07/2022 | COT - LCEL - Electrical Progress | Passed | {Activity date: 06/07/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 05/25/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by VVERA1 - PA. Second floor, except for drops.} ; {Activity date: 01/19/2022; Status: Denied; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - DE. 1-Land all wire assemblies in walls. 2-Bond water piping. CONTACTS: STEVEN SHELL CONTRACTOR: EPSTEIN CONSTRUCTION LLC (520-806-4000- ), No Other Contact listed} |
|
| 06/07/2022 | COT - LCEL - Electrical Intermediate | Passed | {Activity date: 06/07/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 05/25/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by VVERA1 - PA. Second floor.} | |
| 06/07/2022 | COT - LCPL - Plumbing Progress | Passed | {Activity date: 06/07/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 05/25/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by VVERA1 - PA. Second floor, except for drops.} ; {Activity date: 01/19/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - PA. Yard water line. Field 12-2 Texted ETA at 10:00} |
|
| 06/07/2022 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 06/07/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 05/25/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by VVERA1 - PA. Second floor.} ; {Activity date: 05/18/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by VVERA1 - PA. Exterior soffits.} | |
| 08/03/2022 | COT - LCBU - Building Above Ceiling | Passed | {Activity date: 08/03/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - Approved} ; {Activity date: 06/07/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - PA Level One, floor and demising walls.} ; {Activity date: 05/18/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by VVERA1 - PA. Exterior soffits.} | |
| 08/03/2022 | COT - LCME - Mechanical Above Ceiling | Passed | {Activity date: 08/03/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - Approved} ; {Activity date: 07/15/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Partial approval for above ceiling in soffit areas only bldg 4} ; {Activity date: 05/25/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by VVERA1 - PA. Second floor, except for drops.} | |
| 08/03/2022 | COT - LCPL - Plumbing Above Ceiling | Passed | {Activity date: 08/03/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - Approved} ; {Activity date: 07/15/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Partial approval for above ceiling in soffit areas only bldg 4 } ; {Activity date: 06/07/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - PA. Level One, floor and demising walls.} ; {Activity date: 05/25/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by VVERA1 - PA. Second floor, except for drops.} ; {Activity date: 05/18/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by VVERA1 - PA. Exterior soffits.} |
|
| 08/03/2022 | COT - LCEL - Electrical Above Ceiling | Passed | {Activity date: 08/03/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - Approved} ; {Activity date: 07/15/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Partial approval for above ceiling in soffit areas only bldg 4 } ; {Activity date: 06/07/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - PA. Level One, floor and demising walls.} ; {Activity date: 05/25/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by VVERA1 - PA. Second floor, except for drops.} ; {Activity date: 05/18/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by VVERA1 - PA. Exterior soffits.} |
|
| 08/03/2022 | COT - LCME - Mechanical Intermediate | Passed | {Activity date: 08/03/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - Approved} ; {Activity date: 07/15/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Partial approval for above ceiling in soffit areas only bldg 4} ; {Activity date: 06/07/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - -PA Level One, floor and demising walls.} | |
| 08/10/2022 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 08/10/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - Approved} ; {Activity date: 07/21/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - PA. All except level one soffits.} ; {Activity date: 06/30/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - PA. Level one: Second layer of ceiling and demising walls. Level two: dropped ceiling areas. Water heater room.} ; {Activity date: 06/24/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by VVERA1 - PA. Level one: First layer of ceiling. Demising walls. Level two: second layer at ceiling. Demising walls down to soffits.} ; {Activity date: 06/21/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - PA. Level two: second layer of ceiling, walls.} ; {Activity date: 06/10/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - PA. Level Two, first layer of ceiling, demising walls.} | |
| 08/30/2022 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 08/30/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - CODE ECO} | |
| 12/09/2022 | COT - LCEL - Electrical Final | Passed | ||
| 12/09/2022 | COT - LCME - Mechanical Final | Passed | ||
| 12/09/2022 | COT - LCBU - Building Progress | Passed | ||
| 12/09/2022 | COT - LCBU - Firewall/Fire Barrier/Firestop | Passed | ||
| 12/09/2022 | COT - LCBU - Preslab | Passed | ||
| 12/09/2022 | COT - LCPL - Plumbing Final | Passed | ||
| 12/09/2022 | COT - LCME - Mechanical Progress | Passed | ||
| 12/09/2022 | COT - LCPL - Gas Pressure Test | Passed | ||
| 12/09/2022 | COT - LCEL - Outdoor Lighting | Passed | ||
| 12/09/2022 | COT - BULD - SWG Clearance | Passed | Two meters. | |
| 01/05/2023 | COT - FCON - Alarm - Final | Passed | ||
| 01/05/2023 | COT - FCON - Sprinkler - Final | Passed | ||
| 01/11/2023 | COT - FCON - Fire - Final | Passed | OK to obtain TCO. | |
| 09/18/2023 | COT - LCBU - Building Final | Passed |