Permit Details

Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
613 E DELANO ST
Apply Date:
02/09/2021
Applicant:
Ideation Design Group
Description:
FOOD AND BEVERAGE PREPARATION
Architects:
  • Carl F Schaffer
Contractors:
  • GRAIL CONSTRUCTION LLC

Permit Reviews

Permit Number - T21CM01129
Permit Status: C of o
Permit Description: FOOD AND BEVERAGE PREPARATION
Start Date Submittal Complete Date Status  
02/09/2021 COMMERCIAL - TI 03/24/2021 COMPLETED Review Details
04/08/2021 RESUBMITTAL 04/08/2021 COMPLETED Review Details

Completed Inspections

Permit Status: C of o
Permit Number: T21CM01129
Permit Description: FOOD AND BEVERAGE PREPARATION
Total Completed Inspections - 37
Date Description Inspector Results Comments
04/22/2021 PLUMBING - ROUGH, SOIL DQUINN Approved Remainder of underground abs, for bathrooms, ok to backfill.
06/14/2021 GAS CLEARANCE DQUINN Approved CODE
06/14/2021 PLUMBING - GAS PRESSURE TEST DQUINN Approved Ap
Note: manifolds could not be isolated to test. SWG will have to sniff them before ignition.
06/14/2021 MECHANICAL - INTERMEDIATE DQUINN Approved
06/14/2021 PLUMBING - PROGRESS DQUINN Approved
06/14/2021 PLUMBING - INTERMEDIATE DQUINN Approved
06/14/2021 ELECTRIC - INTERMEDIATE DQUINN Approved
06/14/2021 FRAMING DQUINN Approved
07/08/2021 PLUMBING - YARD WTR LINE/TEST DQUINN Approved Ap
Ok to backfill.
07/15/2021 BUILDING ABOVE CEILING DQUINN Approved Ap
All trades above ceiling, including all smoke tests on hood ducting, ok to cover.
07/16/2021 TEP CLEARANCE - PM DQUINN Approved CODE INCR/ NEW SES PANELS L1/L2
07/16/2021 ELECTRIC - SERVICE UPGRADE DQUINN Approved Ap

Clear incr. (new SES to panels L1 and L2)
08/04/2021 ELECTRIC - CONSTRUCTION POWER DQUINN Approved na
08/04/2021 ELECTRIC - UNDERGROUND DQUINN Approved na
08/04/2021 MECHANICAL - ABOVE CEILING DQUINN Approved Ap

No clearances needed
08/04/2021 ELECTRIC - PROGRESS DQUINN Approved Ap

No clearances needed
08/04/2021 BUILDING - PROGRESS DQUINN Approved Ap

No clearances needed
08/04/2021 ELECTRIC - ABOVE CEILING DQUINN Approved Ap

No clearances needed
08/04/2021 ELECTRIC - TEMPORARY SERVICE DQUINN Approved Ap

No clearances needed
08/06/2021 FIRE SPKLR - OH PIPING & HYDRO jfordney Approved per M. Ross 6/7/2021
08/06/2021 FIRE SPKLR - OH PIPING & HYDRO IVR USER Approved IVRS - RI canceled
08/12/2021 FIRE - FINAL wmotto1 Approved
08/12/2021 FIRE - KITCHEN EXH HOOD FINAL wmotto1 Approved
08/12/2021 FIRE - ALARM FINAL wmotto1 Approved
08/12/2021 FIRE SPKLR - FINAL wmotto1 Approved
08/12/2021 FIRE SPKLR - UG PIPING FLUSH wmotto1 Approved
08/12/2021 FIRE SPKLR - UG, PIPING, HYDRO wmotto1 Approved
08/13/2021 MECHANICAL - FINAL DQUINN Approved Ap

Ok for TCO for stocking and training only.
08/13/2021 MECHANICAL - PROGRESS DQUINN Approved Ap
08/13/2021 PLUMBING - ABOVE CEILING DQUINN Approved Ap
08/13/2021 ELECTRIC - FINAL DQUINN Approved Ap
08/13/2021 OUTDOOR LIGHTING FINAL DQUINN Approved Ap
08/17/2021 HEALTH DEPT - FINAL 724-7908 PURBINA Approved
08/17/2021 RIGHT OF WAY - FINAL Bravin Approved no issues with temporary C of O. Issues with handicap ramps and existing driveway apron that was re-paved. Dave Roberts from developmental service is working with construction engineer to resolve the existing issue.
12/20/2021 PLUMBING - FINAL RSHERRY Approved 3-COMPARTMENT SINK NOT USED FOR FOOD PREP, INDEPENDENT INDIRECT DRAINS FROM EACH COMPARTMENT NOT REQUIRED (SECTION 802.1.1, IPC 2018)
12/21/2021 CERTIFICATE OF OCCUPANCY DQUINN Approved
12/21/2021 BUILDING - FINAL RSHERRY Approved REVIEW OF WATER DISINFECTION REPORT COMPLETED

Documents

File Name Document Type  
1 - STRUCTURAL SPECIAI INSPECTIONS CERT 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
APPLICATION 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
GCL 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
JOB CARD 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
PERMIT 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
PLAN_SET 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
T20CM06858_R1 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
T21CM01129 - COFO 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
TCO - 12.16.2021 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
TCO EXTENSION 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
TCO FOR STOCKING 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
1 - STRUCTURAL SPECIAI INSPECTIONS CERT.PDF DOCUMENTS VIEW
T21CM01129 - COFO.PDF DOCUMENTS VIEW
TCO - 12.16.2021.PDF DOCUMENTS VIEW
TCO FOR STOCKING.PDF DOCUMENTS VIEW
TCO EXTENSION.PDF DOCUMENTS VIEW
T20CM06858_R1.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
GCL.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
PLAN_SET.PDF DOCUMENTS VIEW