Permit: T21CM01057
Permit Details
Apply Date:
02/04/2021
Applicant:
BWS Architects
Description:
HEALTH CLINIC
Architects:
- BWS Architects
Contractors:
- Lloyd Construction Company Inc.
Permit Reviews
Permit Number - T21CM01057
Permit Status: C of o
Permit Description: HEALTH CLINIC
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/04/2021 | 3RD PARTY REVIEW - COMMERCIAL TI | 04/07/2021 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T21CM01057
Permit Description: HEALTH CLINIC
Total Completed Inspections - 25
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/24/2021 | PLUMBING - ROUGH, SOIL | JBURGE | Approved | Partial. Waste and vent lines (2”-4”) on GL: 3/B-F (South). Ok to cover progress areas. |
| 08/06/2021 | BUILDING - FINAL | RELEFANTE | Approved | cancel |
| 09/03/2021 | REINFORCED MASONRY PRE-GROUT | JBURGE | Approved | Partial. CMU walls of elevator shaft topped out at 34’. Ok to grout progress areas. |
| 10/14/2021 | FRAMING | JBURGE | Approved | Not ready |
| 10/26/2021 | ELECTRIC - UNDERGROUND | JBURGE | Approved | Partial. Conduits (1” - 2”) for monument sign and lighting for solar canopies. Ok to cover progress areas. |
| 11/05/2021 | SHEET ROCK NAILING | JBURGE | Approved | Approved. Ok to tape and texture throughput. |
| 11/17/2021 | STEM WALL/RETAINING WALL | JBURGE | Approved | Not ready. Contractor cancelled. |
| 11/17/2021 | BUILDING PRE-SLAB | JBURGE | Approved | Partial. Generator pad and equipment pad. Northwest. North ramp with #4 wire mesh reinforced. Ok to place concrete in progress areas. |
| 11/23/2021 | BUILDING - PROGRESS | JBURGE | Approved | . Partial. ADA Ramp and sidewalk at Northwest side of building. Ok to place concrete in progress areas. |
| 11/24/2021 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | Partial. West side ramp and landings. Ok to place concrete in progress areas. |
| 12/08/2021 | TEP CLEARANCE - PM | JBURGE | Approved | CODE ECO |
| 12/08/2021 | ELECTRIC - INTERMEDIATE | JBURGE | Approved | 02035. Partial. Electric equipment to be energized: SES Main Section (5 sets ) 400 KCMIL: 3/0 grounding. T-1 Lugs Primary/Secondary; 3/0 grounding. T-2 Lugs; Primary/Secondary, #4 grounding. Generator - EDS-1, #4 grounding with 200 amp disconnects. ATS-1 and EDS-2 Lugs, Normal/Emergency/Load. Panels: LV1-150 amp; LV2-150amp; LV3-150 amp; LV4-150 amp; LV5-150 amp; 2LV1-200 amp; 2LV2-200 amp; ELV1-200 amp; ELV2- 100 amp; 2ELV1- 100 amp; 2HV2 - 200 amp. CLEARANCE: Code: EC |
| 12/13/2021 | PLUMBING - INTERMEDIATE | JBURGE | Approved | Partial. Level #2, rooms and corridors above ceiling. |
| 12/13/2021 | MECHANICAL - INTERMEDIATE | JBURGE | Approved | Partial. Rooms and corridors on Level #2. |
| 12/29/2021 | BUILDING ABOVE CEILING | JBURGE | Approved | Partial. Areas at GL: 3-8/B-F. |
| 12/29/2021 | ELECTRIC - ABOVE CEILING | JBURGE | Approved | Partial. Areas at GL: 3-8/B-F. |
| 12/29/2021 | PLUMBING - ABOVE CEILING | JBURGE | Approved | Partial. Areas at GL: 3-8/B-F. |
| 12/29/2021 | MECHANICAL - ABOVE CEILING | JBURGE | Approved | Partial. Areas at GL: 3-8/B-F. |
| 03/07/2022 | PLUMBING - FINAL | JBURGE | Approved | Approved |
| 03/07/2022 | PLUMBING - PRE SLAB | JBURGE | Approved | Approved |
| 03/11/2022 | MECHANICAL - FINAL | JBURGE | Approved | Approved. Air balance test results forwarded to Robert Sherry. |
| 03/17/2022 | ELECTRIC - FINAL | JBURGE | Approved | Approved |
| 03/21/2022 | FIRE - FINAL | CBASALDUA | Approved | |
| 03/21/2022 | FIRE - ALARM FINAL | CBASALDUA | Approved | |
| 03/21/2022 | FIRE SPKLR - FINAL | CBASALDUA | Approved |