Inspection History: ELECTRIC - INTERMEDIATE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/07/2022 | ELECTRIC - INTERMEDIATE | Approved | Approved | |
| 12/08/2021 | ELECTRIC - INTERMEDIATE | Partial Approval | 02035. Partial. Electric equipment to be energized: SES Main Section (5 sets ) 400 KCMIL: 3/0 grounding. T-1 Lugs Primary/Secondary; 3/0 grounding. T-2 Lugs; Primary/Secondary, #4 grounding. Generator - EDS-1, #4 grounding with 200 amp disconnects. ATS-1 and EDS-2 Lugs, Normal/Emergency/Load. Panels: LV1-150 amp; LV2-150amp; LV3-150 amp; LV4-150 amp; LV5-150 amp; 2LV1-200 amp; 2LV2-200 amp; ELV1-200 amp; ELV2- 100 amp; 2ELV1- 100 amp; 2HV2 - 200 amp. CLEARANCE: Code: EC |
|
| 11/29/2021 | ELECTRIC - INTERMEDIATE | Partial Approval | Partial. Level #1 electric panels: ELV2 at 125 amps; LV5 at 150 amps; LV4 at 150 amps; HV3 at 200 amps. Level #2 electric panels: 2ELV1 at 100 amps; 2 HV1 at 100 amps; 2 LV1 at 200 amps; 2LV2 at 200 amps. Generator ground connection. | |
| 11/24/2021 | ELECTRIC - INTERMEDIATE | Partial Approval | Partial. LV2, LV3, ELV1; Transformers; exterior electric cabinets; service entrance cabinets #1 and #2. | |
| 09/24/2021 | ELECTRIC - INTERMEDIATE | Partial Approval | Partial. Level #1 all rooms and areas. Exterior light pole caisson footing and rebar cage. Ok to place concrete in progress area. | |
| 09/23/2021 | ELECTRIC - INTERMEDIATE | Not ready for Inspection | Not ready. Contractor cancelled. | |
| 09/22/2021 | ELECTRIC - INTERMEDIATE | Not ready for Inspection | Not ready. Contractor cancelled, will reschedule for 23 September | |
| 09/10/2021 | ELECTRIC - INTERMEDIATE | Partial Approval | Partial. Level #2 completed. | |
| 08/26/2021 | ELECTRIC - INTERMEDIATE | Not ready for Inspection | Not ready. Contractor cancelled. | |
| 08/24/2021 | ELECTRIC - INTERMEDIATE | Not ready for Inspection | Not ready. Contractor cancelled. | |
| 07/15/2021 | ELECTRIC - INTERMEDIATE | Partial Approval | PA( electrical conduit on 2nd floor at this time approved so he can pour concrete) | |
| 07/07/2021 | ELECTRIC - INTERMEDIATE | Partial Approval | Partial. Electric underground communications lines, conduits at 1”-2”. Ok to cover progress areas. | |
| 06/23/2021 | ELECTRIC - INTERMEDIATE | Partial Approval | Partial. Temporary construction power on West side of building (200 amp service). |