Permit: T21CM00795
Permit Details
Apply Date:
01/26/2021
Applicant:
N/A
Description:
RESTAURANT
Architects:
- Sake H. Reindersma
Contractors:
- HENES CONSTRUCTION INC ,
Permit Reviews
Permit Number - T21CM00795
Permit Status: C of o
Permit Description: RESTAURANT
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/26/2021 | COMMERCIAL - NEW | 04/05/2021 | COMPLETED |
04/14/2021 | RESUBMITTAL | 05/14/2021 | COMPLETED |
05/28/2021 | RESUBMITTAL | 05/28/2021 | COMPLETED |
08/31/2021 | REVISION - - 1ST | 09/08/2021 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T21CM00795
Permit Description: RESTAURANT
Total Completed Inspections - 48
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/03/2021 | SITE - SEWER | TGAUSP | Approved | Approved to HCS, okay to backfill |
09/14/2021 | ELECTRIC - UFER | TGAUSP | Approved | Approved |
09/14/2021 | EXCAVATION/LAYOUT REBAR & ZON | TGAUSP | Approved | Approved |
09/21/2021 | PLUMBING - ROUGH, SOIL | TGAUSP | Approved | Approved |
09/27/2021 | BUILDING PRE-SLAB | TGAUSP | Approved | Approved, okay to pour concrete |
10/06/2021 | ELECTRIC - OUTDOOR LIGHTING | TGAUSP | Approved | Approved, okay to pour pole foundations |
10/12/2021 | ELECTRIC - UNDERGROUND | TGAUSP | Approved | Approved underground site lighting, okay to backfill |
10/18/2021 | ROOF NAILING | TGAUSP | Approved | Approved |
10/20/2021 | EXT METAL CLIPS/EXT SHEATHING | TGAUSP | Approved | Approved |
10/20/2021 | FRAMING | TGAUSP | Approved | Approved |
10/20/2021 | ELECTRIC - INTERMEDIATE | TGAUSP | Approved | Approved |
10/20/2021 | PLUMBING - INTERMEDIATE | TGAUSP | Approved | Approved |
10/20/2021 | PLUMBING - ROOF DRAINS | TGAUSP | Approved | Approved |
10/27/2021 | REINFORCED MASONRY PRE-GROUT | TGAUSP | Approved | Approved for 10’x10’ electric room, CMU block walls up to bond beam, okay to grout |
11/01/2021 | SHEET ROCK NAILING | DQUINN | Approved | Ap |
11/16/2021 | TEP CLEARANCE - PM | TGAUSP | Approved | CODE TEC |
11/16/2021 | ELECTRIC - TEMPORARY SERVICE | TGAUSP | Approved | Approved, please TEC Clearance to TEP for temp power |
11/16/2021 | MECHANICAL - ABOVE CEILING | TGAUSP | Approved | Approved |
11/16/2021 | PLUMBING - ABOVE CEILING | TGAUSP | Approved | Approved |
11/16/2021 | ELECTRIC - ABOVE CEILING | TGAUSP | Approved | |
11/16/2021 | BUILDING ABOVE CEILING | TGAUSP | Approved | - Approved, okay to hang tiles |
12/07/2021 | ELECTRIC - FINAL | DMUNIZ | Approved | Approved |
12/09/2021 | FIRE - FINAL | MRoss | Approved | |
12/09/2021 | FIRE - ALARM FINAL | MRoss | Approved | No fire alarm system in building and none is required. |
12/09/2021 | PLUMBING - YARD WTR LINE/TEST | TGAUSP | Approved | previously Approved |
12/10/2021 | BUILDING - FINAL | DMUNIZ | Approved | |
12/10/2021 | STEM WALL/RETAINING WALL | DMUNIZ | Approved | Not Applicable. |
12/10/2021 | U VALUE FOR WINDOW | DMUNIZ | Approved | Not Applicable. |
12/10/2021 | FIREWALL/FIREBARRIER/FIRESTOP | DMUNIZ | Approved | Not Applicable. |
12/10/2021 | ELECTRIC - TEMPORARY POLE | DMUNIZ | Approved | Not Applicable. |
12/10/2021 | ELECTRIC - CONSTRUCTION POWER | DMUNIZ | Approved | Not Applicable. |
12/10/2021 | ELECTRIC - SERVICE UPGRADE | DMUNIZ | Approved | Not Applicable. |
12/10/2021 | PLUMBING - GAS PRESSURE TEST | DMUNIZ | Approved | Not Applicable. |
12/10/2021 | PLUMBING - GAS PRESS TEST FNL | DMUNIZ | Approved | Not Applicable. |
12/10/2021 | SEWER - PRE CONSTRUCTION MTG | DMUNIZ | Approved | Not Applicable. |
12/10/2021 | PLUMBING - GAS RECONNECT | DMUNIZ | Approved | Not Applicable. |
12/10/2021 | MECHANICAL - UNDERGROUND | DMUNIZ | Approved | Not Applicable. |
12/10/2021 | MECHANICAL - HOODS | DMUNIZ | Approved | Not Applicable. |
12/10/2021 | MECHANICAL - HOOD SYSTEMS | DMUNIZ | Approved | Not Applicable. |
12/10/2021 | BUILDING - FINAL | DMUNIZ | Approved | Approved, special Inspection report submitted for approval. Ok for TCO |
12/10/2021 | BUILDING - PROGRESS | DMUNIZ | Approved | Approved. |
12/10/2021 | OUTDOOR LIGHTING FINAL | DMUNIZ | Approved | Approved. |
12/10/2021 | PLUMBING - PROGRESS | DMUNIZ | Approved | Approved. |
12/10/2021 | MECHANICAL - INTERMEDIATE | DMUNIZ | Approved | Approved. |
12/10/2021 | MECHANICAL - PROGRESS | DMUNIZ | Approved | Approved. |
12/13/2021 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER DISINFECTION REPORT COMPLETED |
12/13/2021 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED |
12/15/2021 | PLUMBING - PRE SLAB | aruiz | Approved |