Permit Details

Status:
C of o
Type:
COMMERCIAL ALTERATION
Address NEW:
40 E CONGRESS ST 102
Apply Date:
01/15/2021
Applicant:
Victor Bolduc
Description:
OFFICE
Architects:
  • Thomas Sayler Brown
Contractors:
  • M W Morissey

Permit Reviews

Permit Number - T21CM00516
Permit Status: C of o
Permit Description: OFFICE
Start Date Submittal Complete Date Status  
01/15/2021 COMMERCIAL - TI 02/17/2021 COMPLETED Review Details
02/22/2021 RESUBMITTAL 03/09/2021 COMPLETED Review Details

Completed Inspections

Permit Status: C of o
Permit Number: T21CM00516
Permit Description: OFFICE
Total Completed Inspections - 20
Date Description Inspector Results Comments
03/16/2021 PLUMBING - ROUGH, SOIL JBURGE Approved APPROVED, OK TO COVER PROGRESS AREAS
03/30/2021 BUILDING PRE-SLAB JBURGE Approved Approved. 0k to place concrete in progress areas.
03/30/2021 BUILDING PRE-SLAB JBURGE Approved Approved. Ensure slab area is termite treated.
05/24/2021 MECHANICAL - INTERMEDIATE JBURGE Approved APPROVED LINES SETS IN PLACE
05/24/2021 PLUMBING - INTERMEDIATE JBURGE Approved
05/24/2021 ELECTRIC - INTERMEDIATE JBURGE Approved APPROVED IN WALL ELECTRIC
05/24/2021 FRAMING JBURGE Approved APPROVED OK TO INSULATE AND COVER WALLS
06/09/2021 ELECTRIC - ABOVE CEILING JBURGE Approved Approved. Ok to set ceiling tiles in progress areas.
07/14/2021 TEP CLEARANCE - PM JBURGE Approved CODE ECO/STE 102
08/17/2021 BUILDING ABOVE CEILING JBURGE Approved Approved
08/23/2021 MECHANICAL - FINAL RSHERRY Approved REVIEW OF AIR BALANCE REPORT COMPLETED
08/23/2021 PLUMBING - FINAL RSHERRY Approved REVIEW OF WATER DISINFECTION REPORT COMPLETED
08/30/2021 FIRE - FINAL CBASALDUA Approved
08/30/2021 FIRE - ALARM FINAL CBASALDUA Approved
08/30/2021 FIRE SPKLR - FINAL CBASALDUA Approved
08/30/2021 ELECTRIC - FINAL DQUINN Approved Ap
08/30/2021 BUILDING - PROGRESS DQUINN Approved Ap
09/14/2021 CERTIFICATE OF OCCUPANCY aquiroz Approved
09/14/2021 BUILDING - FINAL aquiroz Approved
09/14/2021 EXCAVATION/LAYOUT REBAR & ZON aquiroz Approved