Permit: T21CM00405
Permit Details
Status:
Final
Type:
MULTI FAMILY ALTERATION
Address:
1341 W PENNINGTON ST
Address NEW:
1341 W PENNINGTON ST
Apply Date:
01/14/2021
Applicant:
WLFA Associates
Description:
Interior facelift, new HVAC, new indoor electrical panel, new laundry and minor expansion. Project valuation is for permit items.
Architects:
- William L. Ford
Contractors:
- WLFA Associates
Permit Reviews
Permit Number - T21CM00405
Permit Status: Final
Permit Description: Interior facelift, new HVAC, new indoor electrical panel, new laundry and minor expansion. Project valuation is for permit items.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/14/2021 | COMMERCIAL - TI | 02/17/2021 | COMPLETED |
| 02/22/2021 | RESUBMITTAL | 03/04/2021 | COMPLETED |
Completed Inspections
Permit Status: Final
Permit Number: T21CM00405
Permit Description: Interior facelift, new HVAC, new indoor electrical panel, new laundry and minor expansion. Project valuation is for permit items.
Total Completed Inspections - 19
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/13/2021 | BUILDING PRE-SLAB | TGUASP | Approved | |
| 04/13/2021 | EXCAVATION/LAYOUT REBAR & ZON | TGAUSP | Approved | APPROVED OK TO POUR CONCRETE |
| 06/17/2021 | PLUMBING - INTERMEDIATE | DQUINN | Approved | |
| 06/17/2021 | ELECTRIC - ABOVE CEILING | DQUINN | Approved | |
| 06/17/2021 | BUILDING ABOVE CEILING | DQUINN | Approved | |
| 06/17/2021 | FRAMING | DQUINN | Approved | |
| 06/21/2021 | MECHANICAL - INTERMEDIATE | JBURGE | Approved | APPROVED AND OK TO INSULATE AND COVER WALLS |
| 06/21/2021 | ELECTRIC - INTERMEDIATE | JBURGE | Approved | APPROVED OK TO INSULATE AND COVER WALLS |
| 06/23/2021 | GAS CLEARANCE | JBURGE | Approved | CODE |
| 06/23/2021 | PLUMBING - GAS PRESSURE TEST | JBURGE | Approved | |
| 06/23/2021 | ELECTRIC - OUTDOOR LIGHTING | JBURGE | Approved | |
| 07/07/2021 | STUCCO MESH | DQUINN | Approved | Ap |
| 07/21/2021 | PLUMBING - ROUGH, SOIL | TGAUSP | Approved | Approved from courtyard to parking lot drain |
| 08/26/2021 | BUILDING - FINAL | DQUINN | Approved | Ap |
| 08/26/2021 | BUILDING - PROGRESS | DQUINN | Approved | Ap |
| 08/26/2021 | ELECTRIC - FINAL | DQUINN | Approved | Ap |
| 08/26/2021 | OUTDOOR LIGHTING FINAL | DQUINN | Approved | Ap |
| 08/26/2021 | PLUMBING - FINAL | DQUINN | Approved | Ap |
| 08/26/2021 | MECHANICAL - FINAL | DQUINN | Approved | Ap |