Permit: T21CM00076
Permit Details
Apply Date:
01/04/2021
Applicant:
BWS Architects
Description:
Tennant Improvement to Approx. 6,600sf of Existing Office Building at 3113 E. 1st Street.
Architects:
- Robin A. Shambach
Contractors:
- Chestnut Building & Design
Permit Reviews
Permit Number - T21CM00076
Permit Status: L of c
Permit Description: Tennant Improvement to Approx. 6,600sf of Existing Office Building at 3113 E. 1st Street.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/05/2021 | COMMERCIAL - TI | 02/04/2021 | COMPLETED |
| 03/10/2021 | RESUBMITTAL | 03/23/2021 | COMPLETED |
Completed Inspections
Permit Status: L of c
Permit Number: T21CM00076
Permit Description: Tennant Improvement to Approx. 6,600sf of Existing Office Building at 3113 E. 1st Street.
Total Completed Inspections - 18
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/15/2021 | PLUMBING - ROUGH, SOIL | RELEFANTE | Approved | |
| 05/14/2021 | PLUMBING - INTERMEDIATE | ESTEVENS | Approved | |
| 06/01/2021 | FRAMING | RELEFANTE | Approved | |
| 06/01/2021 | ELECTRIC - INTERMEDIATE | RELEFANTE | Approved | |
| 08/20/2021 | BUILDING ABOVE CEILING | RELEFANTE | Approved | AP |
| 08/20/2021 | ELECTRIC - ABOVE CEILING | RELEFANTE | Approved | AP |
| 08/20/2021 | MECHANICAL - INTERMEDIATE | RELEFANTE | Approved | AP |
| 09/09/2021 | ELECTRIC - SERVICE UPGRADE | ESTEVENS | Approved | Approved 2090 |
| 09/09/2021 | ELECTRIC - TEMPORARY SERVICE | ESTEVENS | Approved | Approved 2090 |
| 09/09/2021 | BUILDING - PROGRESS | ESTEVENS | Approved | Approved 1090 |
| 09/09/2021 | PLUMBING - GAS PRESSURE TEST | ESTEVENS | Approved | Approved 3090 |
| 09/09/2021 | PLUMBING - FINAL | ESTEVENS | Approved | Approved |
| 09/09/2021 | MECHANICAL - FINAL | ESTEVENS | Approved | Approved |
| 09/09/2021 | ELECTRIC - FINAL | ESTEVENS | Approved | Approved |
| 09/09/2021 | BUILDING - FINAL | ESTEVENS | Approved | Approved |
| 09/09/2021 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED |
| 09/09/2021 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER DISINFECTION REPORT COMPLETED |
| 10/27/2021 | FIRE - FINAL | jfordney | Approved |