Permit Details

Status:
Withdrwn
Type:
COMMERCIAL DEMOLITION
Address:
3400 E ZOO CT
Address NEW:
3400 E ZOO CT
Apply Date:
02/26/2021
Applicant:
Lloyd Construction Co., Inc.
Description:
Roughly 4 acres of demolition at the site of the zoo expansion west of Lakeshore Drive, including removal of large trees, the draining of existing lake and removal of boulders surrounding it, and demolition of existing site lighting. There will also be additional demolition of the current flamingo exhibit at the southwest end of the zoo, to include removal of the existing flamingo pond, paving, and pavilion & watermill structure.
Architects:
  • Torre Design Consortum, LTD
Contractors:
  • LLOYD CONSTRUCTION

Permit Reviews

Permit Number - T21BU00108
Permit Status: Withdrwn
Permit Description: Roughly 4 acres of demolition at the site of the zoo expansion west of Lakeshore Drive, including removal of large trees, the draining of existing lake and removal of boulders surrounding it, and demolition of existing site lighting. There will also be additional demolition of the current flamingo exhibit at the southwest end of the zoo, to include removal of the existing flamingo pond, paving, and pavilion & watermill structure.
Start Date Submittal Complete Date Status  
03/01/2021 COMMERCIAL - BLDG/FIRE/ZONING/ENG 04/22/2021 COMPLETED Review Details

Outstanding Inspections

Permit Status: Withdrwn
Permit Number: T21BU00108
Permite Description: Roughly 4 acres of demolition at the site of the zoo expansion west of Lakeshore Drive, including removal of large trees, the draining of existing lake and removal of boulders surrounding it, and demolition of existing site lighting. There will also be additional demolition of the current flamingo exhibit at the southwest end of the zoo, to include removal of the existing flamingo pond, paving, and pavilion & watermill structure.
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
BUILDING - FINAL N/A Not Inspected