Permit: T20RW04335
Permit Details
Apply Date:
07/28/2020
Applicant:
HUNTER CONTRACTING CO
Description:
PIMA COUNTY REGIONAL WASTEWATER RECLAMATION DEPARTMENT PUBLIC SEWER IMPROVEMENT PLAN MABEL SEWER IMPROVEMENTS (3SAC15) PCRWRD NO. G-2020-027 The improvements will occur along Mabel Street between Sixth and Thirteenth avenues. Hunter Contracting will install new ten-inch diameter sewer lines from Tenth Avenue to Thirteenth Avenue, replace the existing eight-inch diameter sewer lines with new ten-inch lines from Sixth Avenue to Tenth Avenue and install approximately eight new forty-eight-inch diameter manholes. 09/15/2020 - PLAN CHANGE - R1 NIGHT WORK ON MABEL ST AND MAIN AVE. IN THIS PHASE OF THE WORK WE WILL BE DIG ACROSS MAIN AVE AT NIGHT IN ORDER TO INSTALL SEWER LINE. PEDESTRIAN ACCESS MUST BE MAINTAINED PER THE MUTCD CHAPTER 6D. 09/29/2020 - PLAN ADD - R2 LOCATING 12 INCH WATERLINE. WILL NEED TO SET UP A RIGHT LANE SOUTHBOUND CLOSURE IN ORDER TO POTHOLE THE LINE. PEDESTRIAN ACCESS MUST BE MAINTAINED PER THE MUTCD CHAPTER 6D. 10/19/2020 - PLAN CHANGE - R3 SET UP A BYPASS LINE FOR THE SEWER SYSTEM AND WILL HAVE TO USE BIG PUMPS, THAT NEED TO SIT IN THE INTERSECTION. DRACHMAN TO REMAIN OPENED. 10/19/2020 - PLAN CHANGE - R4 24 HOUR CLOSURE ON MABEL ST AND 6TH AV 10/27/2020 - PLAN CHANGE - R5 NIGHT WORK ON MAIN AV & MABEL ST. REQUESTING TO MOVE ALL TRAFFIC TO NORTHBOUND LANE AND USE FLAGGERS. 11/02/2020 - 12/02/2020 APPROVED TNE.
Outstanding Inspections
Permit Status: Final
Permit Number: T20RW04335
Permite Description: PIMA COUNTY REGIONAL WASTEWATER RECLAMATION DEPARTMENT PUBLIC SEWER IMPROVEMENT PLAN
MABEL SEWER IMPROVEMENTS (3SAC15)
PCRWRD NO. G-2020-027
The improvements will occur along Mabel Street between Sixth and Thirteenth avenues. Hunter Contracting will install new ten-inch diameter sewer lines from Tenth Avenue to Thirteenth Avenue, replace the existing eight-inch diameter sewer lines with new ten-inch lines from Sixth Avenue to Tenth Avenue and install approximately eight new forty-eight-inch diameter manholes.
09/15/2020 - PLAN CHANGE - R1
NIGHT WORK ON MABEL ST AND MAIN AVE. IN THIS PHASE OF THE WORK WE WILL BE DIG ACROSS MAIN AVE AT NIGHT IN ORDER TO INSTALL SEWER LINE.
PEDESTRIAN ACCESS MUST BE MAINTAINED PER THE MUTCD CHAPTER 6D.
09/29/2020 - PLAN ADD - R2
LOCATING 12 INCH WATERLINE. WILL NEED TO SET UP A RIGHT LANE SOUTHBOUND CLOSURE IN ORDER TO POTHOLE THE LINE.
PEDESTRIAN ACCESS MUST BE MAINTAINED PER THE MUTCD CHAPTER 6D.
10/19/2020 - PLAN CHANGE - R3
SET UP A BYPASS LINE FOR THE SEWER SYSTEM AND WILL HAVE TO USE BIG PUMPS, THAT NEED TO SIT IN THE INTERSECTION. DRACHMAN TO REMAIN OPENED.
10/19/2020 - PLAN CHANGE - R4
24 HOUR CLOSURE ON MABEL ST AND 6TH AV
10/27/2020 - PLAN CHANGE - R5
NIGHT WORK ON MAIN AV & MABEL ST. REQUESTING TO MOVE ALL TRAFFIC TO NORTHBOUND LANE AND USE FLAGGERS. 11/02/2020 - 12/02/2020 APPROVED TNE.
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/30/2020 | TDOT-EXCAV GENERAL INSPECTION | N/A | Continued | Meeting with Hunter Contracting to discuss keyhole pothole in moratorium section of Stone Av. Will slurry backfill after bore across Stone, replace plug with approved bonding agent. |
| 10/02/2020 | TDOT-Routine Barricade Inspect | N/A | Continued | TDOT-Routine Barricade Inspect (Continued) - Traffic control is set according to plan. |