Inspection Status: Continued
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date |
Description |
Inspector |
Results |
Comments |
| 09/30/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Meeting with Hunter Contracting to discuss keyhole pothole in moratorium section of Stone Av. Will slurry backfill after bore across Stone, replace plug with approved bonding agent. |
| 09/24/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Continued - Sawcut Complete to 10th Av. |
| 09/04/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Continued - Saw cut complete On Mabel from 13th Ave. to Main Avenue. Sewer bypass set up allowing Mabel to 14th Ave. excavation set to begin on Tuesday, September 8. |