Permit: T20CM09337
Permit Details
Apply Date:
12/31/2020
Applicant:
Victor Bolduc / SBBL Architects & Planning, LLC
Description:
OFFICE
Architects:
- Thomas Sayler Brown
Contractors:
- M W Morissey
Permit Reviews
Permit Number - T20CM09337
Permit Status: C of o
Permit Description: OFFICE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/05/2021 | COMMERCIAL - TI | 01/28/2021 | COMPLETED |
01/28/2021 | RESUBMITTAL | 02/09/2021 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T20CM09337
Permit Description: OFFICE
Total Completed Inspections - 20
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/17/2021 | PLUMBING - ROUGH, SOIL | JBURGE | Approved | Approved. Ok to cover progress areas. |
03/30/2021 | BUILDING PRE-SLAB | JBURGE | Approved | Approved. Ensure slab area is termite treated. |
05/24/2021 | MECHANICAL - INTERMEDIATE | JBURGE | Approved | APPROVED LINES SETS IN PLACE |
05/24/2021 | PLUMBING - INTERMEDIATE | JBURGE | Approved | |
05/24/2021 | ELECTRIC - INTERMEDIATE | JBURGE | Approved | APPROVED IN WALL ELECTRIC |
05/24/2021 | FRAMING | JBURGE | Approved | APPROVED TO TO INSULATE AND COVER WALLS |
06/03/2021 | ELECTRIC - ABOVE CEILING | JBURGE | Approved | APPROVED CANNED LIGHT SYSTEM OK TO COVER |
06/03/2021 | BUILDING ABOVE CEILING | JBURGE | Approved | APPROVED OK TO COVER CEILING |
07/14/2021 | TEP CLEARANCE - PM | JBURGE | Approved | CODE ECO/ STE 150 |
07/14/2021 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | Approved |
08/23/2021 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED |
08/30/2021 | FIRE - FINAL | CBASALDUA | Approved | |
08/30/2021 | FIRE - ALARM FINAL | CBASALDUA | Approved | |
08/30/2021 | FIRE SPKLR - FINAL | CBASALDUA | Approved | |
08/30/2021 | BUILDING - PROGRESS | DQUINN | Approved | Ap |
08/30/2021 | PLUMBING - FINAL | DQUINN | Approved | Ap |
08/30/2021 | ELECTRIC - FINAL | DQUINN | Approved | Ap |
08/30/2021 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER DISINFECTION REPORT COMPLETED |
09/13/2021 | CERTIFICATE OF OCCUPANCY | RSHERRY | Approved | |
09/13/2021 | BUILDING - FINAL | RSHERRY | Approved |