Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Expired
Type:
Commercial Building
Address:
3434 S KINO PW
Apply Date:
12/12/2020
Applicant:
Lisa Bowers
Description:
Private Sewer for Bridges B-III

Permit Reviews

Permit Number - T20CM08712
Permit Status: Expired
Permit Description: Private Sewer for Bridges B-III
Start Date Submittal Complete Date Status  
12/12/2020 OTHER 01/13/2021 COMPLETED Review Details

Outstanding Inspections

Permit Status: Expired
Permit Number: T20CM08712
Permite Description: Private Sewer for Bridges B-III
Total Outstanding Inspections - 2
Last Inspection Date Description Inspector Results Comments
11/04/2022 COT - LCPL - Plumbing Final N/A Canceled Inspection Canceled
11/07/2022 PDSD Building Division Pre-Construction Meeting N/A Canceled Inspection Canceled

Completed Inspections

Permit Status: Expired
Permit Number: T20CM08712
Permit Description: Private Sewer for Bridges B-III
Total Completed Inspections - 1
Date Description Inspector Results Comments
03/24/2021 COT - LCPL - Sewer Passed {Activity date: 03/24/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by RSALDAT1 - PA. All except manholes and tests.} ; {Activity date: 03/22/2021; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by VLEON1 - Partially Approved, Manhole #3 NE approx 168’, okay to backfill, Also verified concrete base for Manhole #1} ; {Activity date: 03/19/2021; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by VLEON1 - Partial Approval-PA soil lines continued from Manhole #3 to Manhole #4 and 6” stub out 58’ due SE. okay to backfill} ; {Activity date: 03/18/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VLEON1 - PARTIAL 8 INCH SEWER LINE AND BRANH CONNECTIONS INSTALLED FROM MANHOLE 2-3} ; {Activity date: 03/17/2021; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - Partial Approval-PA soil lines from Manhole #1 to Manhole #2, okay to backfill

} ; {Activity date: 03/16/2021; Status: Not ready for Inspection; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - - NR per contractor} ; {Activity date: 03/15/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VLEON1 - Partial, Interconnection between Public manhole and Private man hole ok to backfill.}

Documents

File Name Document Type  
APPLICATION.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
PLAN SET.PDF DOCUMENTS VIEW
SEWER CONST AUTH.PDF DOCUMENTS VIEW