Inspection Status: Passed
Inspection History: COT - LCPL - Sewer
| Date |
Description |
Inspector |
Results |
Comments |
| 03/24/2021 |
COT - LCPL - Sewer |
RCHANDLER |
Approved |
Entered by RSALDAT1 - PA. All except manholes and tests. |
| 03/22/2021 |
COT - LCPL - Sewer |
TGAUSP |
Partial Approval |
Entered by VLEON1 - Partially Approved, Manhole #3 NE approx 168’, okay to backfill, Also verified concrete base for Manhole #1 |
| 03/19/2021 |
COT - LCPL - Sewer |
TGAUSP |
Partial Approval |
Entered by VLEON1 - Partial Approval-PA soil lines continued from Manhole #3 to Manhole #4 and 6” stub out 58’ due SE. okay to backfill |
| 03/18/2021 |
COT - LCPL - Sewer |
DMUNIZ |
Partial Approval |
Entered by VLEON1 - PARTIAL 8 INCH SEWER LINE AND BRANH CONNECTIONS INSTALLED FROM MANHOLE 2-3 |
| 03/17/2021 |
COT - LCPL - Sewer |
TGAUSP |
Partial Approval |
Entered by RSALDAT1 - Partial Approval-PA soil lines from Manhole #1 to Manhole #2, okay to backfill
|
| 03/16/2021 |
COT - LCPL - Sewer |
TGAUSP |
Not ready for Inspection |
Entered by RSALDAT1 - - NR per contractor |
| 03/15/2021 |
COT - LCPL - Sewer |
DMUNIZ |
Partial Approval |
Entered by VLEON1 - Partial, Interconnection between Public manhole and Private man hole ok to backfill. |