Permit Reviews
Permit Number - T20CM05977
Permit Status: Expired
Permit Description: TENANT REFRESH OF RETAIL SALES AREA
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
08/24/2020 | COMMERCIAL - TI | 01/14/2021 | ACTIVE |
Outstanding Activity Conditions
Permit Number - T20CM05977
Permit Status: Expired
Permit Description: TENANT REFRESH OF RETAIL SALES AREA
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
09/05/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Outstanding Inspections
Permit Status: Expired
Permit Number: T20CM05977
Permite Description: TENANT REFRESH OF RETAIL SALES AREA
Total Outstanding Inspections - 2
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/07/2022 | COT - LCBU - Building Final | N/A | Canceled | Inspection Canceled |
11/07/2022 | COT - LCEL - Electrical Underground | N/A | Canceled | Inspection Canceled |
Completed Inspections
Permit Status: Expired
Permit Number: T20CM05977
Permit Description: TENANT REFRESH OF RETAIL SALES AREA
Total Completed Inspections - 15
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/18/2021 | COT - LCME - Mechanical Above Ceiling | Passed | {Activity date: 06/18/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by VLEON1 - } | |
06/18/2021 | COT - LCEL - Electrical Above Ceiling | Passed | {Activity date: 06/18/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by VLEON1 - } | |
07/01/2021 | COT - LCEL - Electrical Intermediate | Passed | {Activity date: 07/01/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - Approved} ; {Activity date: 06/14/2021; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by VLEON1 - Partial. Phase 1, west side.} | |
07/01/2021 | COT - LCBU - Framing | Passed | {Activity date: 07/01/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - Approved} ; {Activity date: 06/14/2021; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by VLEON1 - Partial. Phase 1, west side.} | |
12/14/2021 | COT - LCEL - Electrical Progress | Passed | {Activity date: 12/14/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} | |
12/14/2021 | COT - LCME - Mechanical Final | Passed | {Activity date: 12/14/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} | |
12/14/2021 | COT - LCEL - Electrical Final | Passed | {Activity date: 12/14/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} | |
12/14/2021 | COT - LCBU - Building Progress | Passed | {Activity date: 12/14/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} | |
01/13/2022 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 01/13/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by NGARCIA3 - FINAL IS APPROVED } |
|
01/13/2022 | PDSD Site/Engineering Division - NPPO | Passed | {Activity date: 01/13/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by NGARCIA3 - FINAL IS APPROVED } |
|
01/13/2022 | PDSD Building Division - Sign Final | Passed | {Activity date: 01/13/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by NGARCIA3 - FINAL IS APPROVED } |
|
01/19/2022 | TRSP - ROW - Final/Close-Out | Passed | {Activity date: 01/19/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
01/19/2022 | ENGR Engineering Final | Passed | {Activity date: 01/19/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 01/13/2022; Status: Partial Approval; Inspector: DROBERTS; Comment: Entered by NGARCIA3 - FINAL IS PARTIAL, OK FOR TCO BUT NOT FOR THE FINAL. THERE IS EXTERIOR WORK HAPPENING ON THE EAST AND NORTH SIDE OF THE EXISTING STRUCTURE THAT SHOULD REQUIRE THAT A DEVELOPMENT PACKAGE PERMIT BE ISSUED. THE ENGINEERING FINAL WILL NOT BE APPROVED TILL THE FOLLOWING ITEMS ARE ADDRESSED: TALK WITH THE ENGINEERING AND ZONING REVIEW STAFF TO DETERMINE IF A DEVELOPMENT PACKAGE AND/OR WALL PERMIT IS REQUIRED FOR THE WALL THAT IS UNDER CONSTRUCTION. DISCUSS THE MODIFICATIONS TO T;HE EXISTING DRAINAGE PATTERNS FOR THIS SITE AND THE SURROUNDING AREAS.} | |
02/04/2022 | COT - FCON - Sprinkler - Final | Passed | {Activity date: 02/04/2022; Status: Approved; Inspector: CBASALDUA; Comment: Entered by CBASALD1 - } ; {Activity date: 10/11/2021; Status: Prior to Final Inspectn; Inspector: JPEELDAVIS; Comment: Entered by JPEELDA1 - Metro relocated/recentered...paper permit for work required to pass fire final.} | |
02/04/2022 | COT - FCON - Fire - Final | Passed | {Activity date: 02/04/2022; Status: Approved; Inspector: CBASALDUA; Comment: Entered by CBASALD1 - } ; {Activity date: 10/12/2021; Status: Cancelled; Inspector: jfordney; Comment: Entered by JFORDNE1 - no sprinkler permit} |