Permit: T20CM05702
Permit Details
Apply Date:
08/31/2020
Applicant:
BILLIE MEUSHCKE
Description:
TENANT IMPROVEMENT
Permit Reviews
Permit Number - T20CM05702
Permit Status: Final
Permit Description: TENANT IMPROVEMENT
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/20/2021 | RESUBMITTAL - TI ALL | 05/11/2021 | COMPLETED |
| 06/04/2021 | RESUBMITTAL | 06/21/2021 | COMPLETED |
| 06/23/2021 | RESUBMITTAL | 06/25/2021 | COMPLETED |
| 08/10/2020 | COMMERCIAL - TI | 01/21/2021 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM05702
Permit Status: Final
Permit Description: TENANT IMPROVEMENT
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/31/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T20CM05702
Permit Description: TENANT IMPROVEMENT
Total Completed Inspections - 18
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/31/2021 | GAS CLEARANCE | TGAUSP | Approved | CODE |
| 08/31/2021 | PLUMBING - GAS PRESSURE TEST | TGAUSP | Approved | Approved, please send clearance to SWG for meter set |
| 09/23/2021 | BUILDING - PROGRESS | TGAUSP | Approved | Approved for infill foundation and slab (detail 2/A2.0) |
| 09/23/2021 | PLUMBING - ROUGH, SOIL | TGAUSP | Approved | Approved connected into 4” main line, okay to cover |
| 10/15/2021 | PLUMBING - INTERMEDIATE | JBURGE | Approved | Approved |
| 10/15/2021 | ELECTRIC - INTERMEDIATE | JBURGE | Approved | Approved |
| 10/15/2021 | FRAMING | JBURGE | Approved | Approved |
| 10/26/2021 | SHEET ROCK NAILING | TGAUSP | Approved | - Approved |
| 10/26/2021 | BUILDING ABOVE CEILING | TGAUSP | Approved | NA |
| 03/02/2022 | PLUMBING - FINAL | TGAUSP | Approved | Approved |
| 03/02/2022 | ELECTRIC - FINAL | TGAUSP | Approved | Approved |
| 03/02/2022 | MECHANICAL - FINAL | TGAUSP | Approved | Approved, existing units |
| 03/17/2022 | MECHANICAL - INTERMEDIATE | TGAUSP | Approved | Approved 4090 |
| 03/17/2022 | OUTDOOR LIGHTING FINAL | TGAUSP | Approved | Approved 2090 |
| 03/17/2022 | ELECTRIC - OUTDOOR LIGHTING | TGAUSP | Approved | Approved 2090 |
| 03/17/2022 | ELECTRIC - ABOVE CEILING | TGAUSP | Approved | Approved 2090 |
| 03/17/2022 | BUILDING - FINAL | TGAUSP | Approved | Approved, pending Letter of Completion and Fire final |
| 03/17/2022 | FIRE - FINAL | jfordney | Approved |