Permit: T20CM05681
Permit Details
Apply Date:
08/30/2020
Applicant:
STEPHEN BOHN
Description:
8 UNIT APARTMENT COMPLEX
Contractors:
- LARRY RAY OLSON
Permit Reviews
Permit Number - T20CM05681
Permit Status: C of o
Permit Description: 8 UNIT APARTMENT COMPLEX
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/17/2021 | RESUBMITTAL | 02/17/2021 | COMPLETED |
| 08/05/2020 | COMMERCIAL - NEW | 10/07/2020 | COMPLETED |
| 11/06/2020 | RESUBMITTAL | 01/11/2021 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM05681
Permit Status: C of o
Permit Description: 8 UNIT APARTMENT COMPLEX
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/30/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T20CM05681
Permit Description: 8 UNIT APARTMENT COMPLEX
Total Completed Inspections - 33
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/24/2021 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | APPROVED |
| 03/05/2021 | ELECTRIC - UNDERGROUND | DQUINN | Approved | |
| 03/11/2021 | BUILDING PRE-SLAB | DQUINN | Approved | |
| 03/30/2021 | EXT METAL CLIPS/EXT SHEATHING | RELEFANTE | Approved | |
| 05/27/2021 | ELECTRIC - CONSTRUCTION POWER | RELEFANTE | Approved | APPROVED NO TEP CLEARANCE REQURESTED |
| 05/27/2021 | ELECTRIC - TEMPORARY SERVICE | RELEFANTE | Approved | APPROVED NO TEP CLEARANCE REQUESTED |
| 05/27/2021 | MECHANICAL - INTERMEDIATE | RELEFANTE | Approved | |
| 05/27/2021 | PLUMBING - INTERMEDIATE | RELEFANTE | Approved | |
| 05/27/2021 | ELECTRIC - INTERMEDIATE | RELEFANTE | Approved | |
| 05/27/2021 | FIREWALL/FIREBARRIER/FIRESTOP | RELEFANTE | Approved | |
| 05/27/2021 | U VALUE FOR WINDOW | RELEFANTE | Approved | |
| 05/27/2021 | BUILDING ABOVE CEILING | RELEFANTE | Approved | |
| 05/27/2021 | FRAMING | RELEFANTE | Approved | |
| 11/16/2021 | STEM WALL/RETAINING WALL | DQUINN | Approved | na |
| 11/16/2021 | PLUMBING - YARD WTR LINE/TEST | DQUINN | Approved | Ap |
| 11/16/2021 | PLUMBING - SEWER HCS CONNECT | DQUINN | Approved | Ap |
| 11/16/2021 | ROOF NAILING | DQUINN | Approved | Ap |
| 11/16/2021 | BUILDING - PROGRESS | DQUINN | Approved | Ap |
| 11/16/2021 | ELECTRIC - ABOVE CEILING | DQUINN | Approved | Ap |
| 12/13/2021 | ELECTRIC - FINAL | DQUINN | Approved | Ap |
| 12/13/2021 | OUTDOOR LIGHTING FINAL | DQUINN | Approved | Ap |
| 12/13/2021 | FIRE SPKLR - UG, PIPING, HYDRO | DQUINN | Approved | Ap The above 4 fire inspections are Ap by me - per C Basaldua’s instructions. |
| 12/13/2021 | FIRE SPKLR - UG PIPING FLUSH | DQUINN | Approved | Ap The above 4 fire inspections are Ap by me - per C Basaldua’s instructions. |
| 12/13/2021 | FIRE SPKLR - OH PIPING & HYDRO | DQUINN | Approved | Ap The above 4 fire inspections are Ap by me - per C Basaldua’s instructions. |
| 12/13/2021 | FIRE SPKLR - FINAL | DQUINN | Approved | Ap The above 4 fire inspections are Ap by me - per C Basaldua’s instructions. |
| 12/20/2021 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED |
| 12/21/2021 | FIRE - FINAL | DQUINN | Approved | na - results are on a separate fire permit. |
| 12/21/2021 | PLUMBING - FINAL | DQUINN | Approved | Ap |
| 12/21/2021 | ELECTRIC - OUTDOOR LIGHTING | DQUINN | Approved | Ap |
| 12/27/2021 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | 1090 Ap |
| 12/27/2021 | ELECTRIC - UFER | DQUINN | Approved | 1090 Ap |
| 12/27/2021 | BUILDING - FINAL | DQUINN | Approved | Ap |
| 12/27/2021 | CERTIFICATE OF OCCUPANCY | DQUINN | Approved | Ap Close permit and ok for C of O |