Permit: T20CM05644
Permit Details
Apply Date:
08/29/2020
Applicant:
N/A
Description:
FIRE STATION #9
Architects:
- POWERS, KENNETH WILLIAM
Contractors:
- CORE CONSTRUCTION SERVICES OF AZ ***APA***
Permit Reviews
Permit Number - T20CM05644
Permit Status: C of o
Permit Description: FIRE STATION #9
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/03/2021 | RESUBMITTAL | 02/11/2021 | COMPLETED |
| 02/25/2021 | RESUBMITTAL | 03/08/2021 | COMPLETED |
| 08/03/2020 | COMMERCIAL - NEW | 09/21/2020 | COMPLETED |
| 11/01/2021 | REVISION - - 1ST | 11/10/2021 | COMPLETED |
| 11/03/2020 | RESUBMITTAL | 12/30/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM05644
Permit Status: C of o
Permit Description: FIRE STATION #9
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/29/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T20CM05644
Permit Description: FIRE STATION #9
Total Completed Inspections - 50
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/14/2021 | TEP CLEARANCE - PM | TTREMBULAK | Approved | CODE TMPP |
| 04/14/2021 | ELECTRIC - TEMPORARY SERVICE | TTREMBULAK | Approved | |
| 06/25/2021 | STEM WALL/RETAINING WALL | WGALLAGHER | Approved | Partial approval for Light duty storage bay and large appliance bay and storage bay stem wall up 2 courses, finish floor elevation, ok to grout |
| 07/23/2021 | BUILDING - PROGRESS | RELEFANTE | Approved | AP |
| 08/03/2021 | BUILDING PRE-SLAB | RELEFANTE | Approved | AP |
| 08/03/2021 | PLUMBING - PRE SLAB | RELEFANTE | Approved | AP |
| 11/01/2021 | PLUMBING - ROUGH, SOIL | RCHANDLER | Approved | PA. West bay trench drain rough-ins. |
| 11/09/2021 | ELECTRIC - UNDERGROUND | RCHANDLER | Approved | AP |
| 11/09/2021 | ROOF NAILING | ENEWCOMB | Approved | |
| 11/18/2021 | REINFORCED MASONRY PRE-GROUT | RCHANDLER | Approved | -AP. Knee wall at workout and West wall of Light duty bay; top out. Equipment room; 3rd lift. |
| 12/02/2021 | EXT METAL CLIPS/EXT SHEATHING | RCHANDLER | Approved | AP. Roof Nailing for Rooms 102, 106, 107, 108, 109, 111, and 114. |
| 12/02/2021 | EXCAVATION/LAYOUT REBAR & ZON | RCHANDLER | Approved | -AP. Apparatus Bay slab and column footing North of Apparatus Bay. |
| 12/13/2021 | PLUMBING - INTERMEDIATE | RCHANDLER | Approved | PA. West dorm rooms and area South of West dorm rooms |
| 12/28/2021 | PLUMBING - ROOF DRAINS | RCHANDLER | Approved | PA Captain’s quarters, apparatus bat, and West side. |
| 12/28/2021 | ELECTRIC - INTERMEDIATE | RCHANDLER | Approved | PA. Captain’s quarters. |
| 12/28/2021 | FRAMING | RCHANDLER | Approved | PA. Captain’s quarters. |
| 12/29/2021 | MECHANICAL - ABOVE CEILING | RCHANDLER | Approved | PA. Duct sealing for Captain’s quarters and rooms 131, 133, 134, 136, 137, 138, 139, and 165. |
| 02/10/2022 | MECHANICAL - HOODS | RCHANDLER | Approved | AP |
| 02/24/2022 | FIREWALL/FIREBARRIER/FIRESTOP | RCHANDLER | Approved | AP Sent text at 8:06 12:30 |
| 02/28/2022 | MECHANICAL - PROGRESS | RCHANDLER | Approved | AP. Smoke test. |
| 02/28/2022 | PLUMBING - GAS PRESSURE TEST | RCHANDLER | Approved | AP |
| 04/07/2022 | PLUMBING - SEWER HCS CONNECT | RCHANDLER | Approved | AP |
| 04/18/2022 | GAS CLEARANCE | RCHANDLER | Approved | CODE |
| 04/18/2022 | PLUMBING - GAS PRESS TEST FNL | RCHANDLER | Approved | AP. SWG clearance. |
| 05/13/2022 | BUILDING ABOVE CEILING | RCHANDLER | Approved | AP |
| 05/13/2022 | STUCCO MESH | RCHANDLER | Approved | AP |
| 05/13/2022 | U VALUE FOR WINDOW | RCHANDLER | Approved | AP |
| 05/13/2022 | ELECTRIC - PROGRESS | RCHANDLER | Approved | AP |
| 05/13/2022 | ELECTRIC - UFER | RCHANDLER | Approved | AP |
| 05/13/2022 | ELECTRIC - ABOVE CEILING | RCHANDLER | Approved | AP |
| 05/13/2022 | ELECTRIC - CONSTRUCTION POWER | RCHANDLER | Approved | AP |
| 05/13/2022 | ELECTRIC - SERVICE UPGRADE | RCHANDLER | Approved | AP |
| 05/13/2022 | ELECTRIC - OUTDOOR LIGHTING | RCHANDLER | Approved | AP |
| 05/13/2022 | OUTDOOR LIGHTING FINAL | RCHANDLER | Approved | AP |
| 05/13/2022 | PLUMBING - ABOVE CEILING | RCHANDLER | Approved | AP |
| 05/13/2022 | PLUMBING - YARD WTR LINE/TEST | RCHANDLER | Approved | AP |
| 05/13/2022 | MECHANICAL - INTERMEDIATE | RCHANDLER | Approved | AP |
| 05/13/2022 | ELECTRIC - FINAL | RCHANDLER | Approved | AP |
| 05/20/2022 | FIRE - ALARM FINAL | CGates | Approved | |
| 05/25/2022 | FIRE SPKLR - OH PIPING & HYDRO | CGates | Approved | Approved by MRoss on 3/21/22. Permit #T21FC00393 |
| 05/25/2022 | FIRE SPKLR - UG PIPING FLUSH | CGates | Approved | Approved by JFordney on 2/11/22. Pemit #T21FC00793 |
| 05/25/2022 | FIRE SPKLR - UG, PIPING, HYDRO | CGates | Approved | Approved by JFordney on 1/7/22 permit #T21FC00793 |
| 05/25/2022 | FIRE - KITCHEN EXH HOOD FINAL | CGates | Approved | |
| 05/25/2022 | FIRE SPKLR - FINAL | CGates | Approved | |
| 10/13/2022 | ENGINEERING - FINAL | DROBERTS | Approved | APPROVED |
| 10/13/2022 | FIRE - FINAL | CGates | Approved | |
| 10/13/2022 | CERTIFICATE OF OCCUPANCY | RCHANDLER | Approved | AP. No access to inspection records. |
| 10/13/2022 | MECHANICAL - FINAL | RCHANDLER | Approved | AP. No access to inspection records. |
| 10/13/2022 | PLUMBING - FINAL | RCHANDLER | Approved | AP. No access to inspection records. |
| 10/13/2022 | BUILDING - FINAL | RCHANDLER | Approved | AP. No access to inspection records. |