Permit: T20CM04953
Permit Details
Status:
L of c
Type:
COMMERCIAL ALTERATION
Address:
3700 E FORT LOWELL RD #130
Address NEW:
3700 E FORT LOWELL RD #130
Apply Date:
07/31/2020
Applicant:
A23 STUDIOS
Description:
MEDICAL OUTPATIENT TENANT IMPROVEMENT
Architects:
- A23 STUDIOS
Permit Reviews
Permit Number - T20CM04953
Permit Status: L of c
Permit Description: MEDICAL OUTPATIENT TENANT IMPROVEMENT
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/06/2020 | 3RD PARTY REVIEW - COMMERCIAL TI | 09/22/2020 | COMPLETED |
| 09/24/2020 | RESUBMITTAL | 10/14/2020 | COMPLETED |
| 10/15/2020 | 3RD PARTY REVIEW - REVISION/OTHER | 10/15/2020 | COMPLETED |
| 12/07/2020 | 3RD PARTY REVIEW - REVISION/OTHER | 12/30/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM04953
Permit Status: L of c
Permit Description: MEDICAL OUTPATIENT TENANT IMPROVEMENT
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/31/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T20CM04953
Permit Description: MEDICAL OUTPATIENT TENANT IMPROVEMENT
Total Completed Inspections - 32
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/23/2020 | BUILDING PRE-SLAB | DQUINN | Approved | |
| 10/23/2020 | PLUMBING - PRE SLAB | DQUINN | Approved | |
| 10/23/2020 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | |
| 10/23/2020 | ELECTRIC - UNDERGROUND | DQUINN | Approved | |
| 10/28/2020 | PLUMBING - PROGRESS | DQUINN | Approved | Called Rick 6x. Got message machine each time and left 3 messages. Unusual behavior to not hear back. Left message to reschedule. Hope all are ok at site? |
| 12/10/2020 | ELECTRIC - FINAL | TGUASP | Approved | Inspections not ready, will need to reschedule. |
| 12/10/2020 | BUILDING - FINAL | TGUASP | Approved | Inspections not ready, will need to reschedule. |
| 12/14/2020 | PLUMBING - INTERMEDIATE | DQUINN | Approved | PARTIAL, NORTH OF GLUE LAM. |
| 12/16/2020 | BUILDING - PROGRESS | ESTEVENS | Approved | Partial. Sheetrock Shearwall nailing on south section |
| 12/18/2020 | ELECTRIC - INTERMEDIATE | JBURGE | Approved | Partial, all areas except for the vault area. |
| 12/28/2020 | FRAMING | JBURGE | Approved | Partial. Vault area parapet walls; extended to accommodate trusses over vault. Ok to cover progress areas. |
| 02/22/2021 | BUILDING ABOVE CEILING | DQUINN | Approved | APPROVED |
| 02/24/2021 | ELECTRIC - PROGRESS | DQUINN | Approved | APPROVED |
| 02/24/2021 | EXT METAL CLIPS/EXT SHEATHING | DQUINN | Approved | APPROVED |
| 02/24/2021 | MECHANICAL - FINAL | DQUINN | Approved | APPROVED |
| 02/24/2021 | ELECTRIC - ABOVE CEILING | DQUINN | Approved | APPROVED |
| 02/24/2021 | SHEET ROCK NAILING | DQUINN | Approved | APPROVED |
| 02/24/2021 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | APPROVED |
| 02/24/2021 | PLUMBING - FINAL | DQUINN | Approved | APPROVED |
| 02/24/2021 | ELECTRIC - SERVICE UPGRADE | DQUINN | Approved | APPROVED |
| 02/25/2021 | RIGHT OF WAY - FINAL | DR | Approved | |
| 02/25/2021 | FIRE SPKLR - FINAL | wmotto1 | Approved | |
| 02/26/2021 | FIRE - ALARM FINAL | wmotto1 | Approved | |
| 03/17/2021 | FIRE - FINAL | ASMITH6 | Approved | Knoxbox and caps have been installed along with FACP and FDC signs. |
| 03/18/2021 | PLUMBING - ABOVE CEILING | DQUINN | Approved | 3090 |
| 03/18/2021 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | 4090 |
| 03/18/2021 | MECHANICAL - ABOVE CEILING | DQUINN | Approved | 4090 |
| 03/18/2021 | MECHANICAL - PROGRESS | DQUINN | Approved | 4090 |
| 03/18/2021 | NPPO - FINAL | DROBERTS | Approved | |
| 03/18/2021 | SIGN - FINAL | DROBERTS | Approved | |
| 03/18/2021 | LANDSCAPE - FINAL | DROBERTS | Approved | |
| 03/18/2021 | ENGINEERING - FINAL | DROBERTS | Approved |