Permit: T20CM04838
Permit Details
Status:
Issued
Type:
Residential Building - One or Two Family
Address:
2334 S NORRIS AV
Address NEW:
2334 S NORRIS AV
Apply Date:
07/28/2020
Applicant:
Description:
MASTER BEDROOOM ADDITION AND REMODEL
Permit Reviews
Permit Number - T20CM04838
Permit Status: Issued
Permit Description: MASTER BEDROOOM ADDITION AND REMODEL
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/11/2021 | RESUBMITTAL | 03/30/2021 | COMPLETED |
| 03/30/2021 | RESUBMITTAL | 04/16/2021 | COMPLETED |
| 06/23/2020 | RESIDENTIAL - BLDG/WWM | 08/05/2020 | COMPLETED |
| 08/05/2020 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 10/07/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM04838
Permit Status: Issued
Permit Description: MASTER BEDROOOM ADDITION AND REMODEL
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/28/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Outstanding Inspections
Permit Status: Issued
Permit Number: T20CM04838
Permite Description: MASTER BEDROOOM ADDITION AND REMODEL
Total Outstanding Inspections - 4
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2022 | COT - RSPL - Yard Water Line | N/A | Not Ready | |
| 10/27/2022 | RSBU - Building Final | N/A | Not Ready | |
| 10/27/2022 | COT - RSPL - Plumbing Final | N/A | Not Ready | |
| 10/27/2022 | COT - RSEL - Electrical Final | N/A | Not Ready |
Completed Inspections
Permit Status: Issued
Permit Number: T20CM04838
Permit Description: MASTER BEDROOOM ADDITION AND REMODEL
Total Completed Inspections - 9
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/28/2021 | COT - RSPL - Rough Soil | Passed | {Activity date: 04/28/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved} | |
| 05/17/2021 | COT - RSBU - Preslab | Passed | {Activity date: 05/17/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by VLEON1 - APPROVED OK TO POUR} | |
| 05/17/2021 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 05/17/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by VLEON1 - } | |
| 09/03/2021 | COT - RSBU - Roof Nailing | Passed | {Activity date: 09/03/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved, okay to roof} | |
| 09/20/2021 | COT - LCBU - Framing | Passed | {Activity date: 09/20/2021; Status: Approved; Inspector: TAGUSP; Comment: Entered by VVERA1 - Approved} ; {Activity date: 09/03/2021; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by VVERA1 - Partial approval for addition only, replace pressure treated bottom plates at patio enclosure } |
|
| 09/20/2021 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | {Activity date: 09/20/2021; Status: Approved; Inspector: TAGUSP; Comment: Entered by VVERA1 - Approved} | |
| 12/17/2021 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 12/17/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved M,P,E, okay to insulate and drywall} ; {Activity date: 12/13/2021; Status: Not ready for Inspection; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - NR, verify electrical outlet spacing, fire blocking, pending plumbing completion and testing. Please reschedule inspection} | |
| 07/21/2022 | COT - RSME - Mechanical Final | Passed | {Activity date: 07/21/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} | |
| 07/21/2022 | COT - RSEL - Outdoor Lighting | Passed | {Activity date: 07/21/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} |