Permit: T20CM04388
Permit Details
Apply Date:
07/13/2020
Applicant:
VENEZIANO, PHILIP JOHN
Description:
NEW SINGLE STORY BUILDING
Architects:
- VENEZIANO, PHILIP JOHN
Permit Reviews
Permit Number - T20CM04388
Permit Status: C of o
Permit Description: NEW SINGLE STORY BUILDING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/13/2020 | COMMERCIAL - NEW | 08/31/2020 | COMPLETED |
| 09/04/2020 | RESUBMITTAL | 10/12/2020 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T20CM04388
Permit Description: NEW SINGLE STORY BUILDING
Total Completed Inspections - 29
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/15/2020 | PLUMBING - ROUGH, SOIL | ESTEVENS | Approved | . Approved. |
| 10/15/2020 | PLUMBING - INTERMEDIATE | ESTEVENS | Approved | Not ready, not complete. |
| 10/23/2020 | ELECTRIC - UFER | DQUINN | Approved | Ap 3 separate ufers. |
| 10/23/2020 | BUILDING PRE-SLAB | DQUINN | Approved | Ap |
| 10/23/2020 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | Ap |
| 11/12/2020 | REINFORCED MASONRY PRE-GROUT | ESTEVENS | Approved | Approved. 12 feet to top-out. |
| 12/14/2020 | ROOF NAILING | DQUIN | Approved | APPROVED. |
| 03/16/2021 | TEP CLEARANCE - PM | ESTEVENS | Approved | CODE ECO |
| 03/16/2021 | BUILDING ABOVE CEILING | ESTEVENS | Approved | |
| 03/16/2021 | ELECTRIC - ABOVE CEILING | ESTEVENS | Approved | |
| 03/16/2021 | ELECTRIC - CONSTRUCTION POWER | ESTEVENS | Approved | |
| 03/24/2021 | PLUMBING - FINAL | ESTEVENS | Approved | Approved. |
| 03/26/2021 | OUTDOOR LIGHTING FINAL | DQUIN | Approved | |
| 03/26/2021 | ELECTRIC - OUTDOOR LIGHTING | DQUIN | Approved | |
| 03/30/2021 | FIRE - FINAL | CBASALDUA | Approved | |
| 04/01/2021 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | |
| 04/01/2021 | FRAMING | DQUINN | Approved | |
| 07/16/2021 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | Ap |
| 07/16/2021 | MECHANICAL - FINAL | DQUINN | Approved | Ap |
| 07/16/2021 | RIGHT OF WAY - FINAL | DQUINN | Approved | Ap- per R of W inspector Dan |
| 07/16/2021 | ENGINEERING - FINAL | BBENEDON | Approved | Approved |
| 08/09/2021 | EXT METAL CLIPS/EXT SHEATHING | DQUINN | Approved | 1090 Ap Ok for C of O Close permit |
| 08/09/2021 | ELECTRIC - UNDERGROUND | DQUINN | Approved | 1090 Ap Ok for C of O Close permit |
| 08/09/2021 | ELECTRIC - FINAL | DQUINN | Approved | 1090 Ap Ok for C of O Close permit |
| 08/09/2021 | ELECTRIC - SERVICE UPGRADE | DQUINN | Approved | 1090 Ap Ok for C of O Close permit |
| 08/09/2021 | LANDSCAPE - FINAL | MHERNANDEZ | Approved | APPROVED |
| 08/09/2021 | SIGN - FINAL | MHERNANDEZ | Approved | APPROVED |
| 08/09/2021 | NPPO - FINAL | MHERNANDEZ | Approved | APPROVED |
| 11/30/2021 | BUILDING - FINAL | aruiz | Approved |