Permit: T20CM03992
Permit Details
Status:
L of c
Type:
COMMERCIAL ALTERATION
Address:
1129 N PALO VERDE BL
Address NEW:
1129 N PALO VERDE BL
Apply Date:
06/25/2020
Applicant:
CATALANO, VINCENT VICTOR
Description:
TI: FITNESS CENTER
Architects:
- CATALANO, VINCENT VICTOR
Permit Reviews
Permit Number - T20CM03992
Permit Status: L of c
Permit Description: TI: FITNESS CENTER
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/25/2020 | COMMERCIAL - TI | 08/19/2020 | COMPLETED |
| 08/24/2020 | RESUBMITTAL | 09/11/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM03992
Permit Status: L of c
Permit Description: TI: FITNESS CENTER
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/25/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T20CM03992
Permit Description: TI: FITNESS CENTER
Total Completed Inspections - 16
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/15/2020 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | Ap |
| 09/15/2020 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | Ap |
| 09/15/2020 | FRAMING | DQUINN | Approved | Ap |
| 09/18/2020 | BUILDING - PROGRESS | TTREMBULAK | Approved | Approved |
| 09/18/2020 | ELECTRIC - ABOVE CEILING | TTREMBULAK | Approved | Approved |
| 09/18/2020 | BUILDING ABOVE CEILING | TTREMBULAK | Approved | Approved |
| 09/18/2020 | MECHANICAL - INTERMEDIATE | TTREMBULAK | Approved | Approved |
| 09/18/2020 | PLUMBING - INTERMEDIATE | TTREMBULAK | Approved | Approved |
| 10/23/2020 | FIRE - FINAL | wmotto | Approved | 1. removed hasp off rear exit door on the south west side. 2. Added one fire extinguisher. |
| 10/23/2020 | OUTDOOR LIGHTING FINAL | ESTEVENS | Approved | |
| 10/23/2020 | ELECTRIC - OUTDOOR LIGHTING | ESTEVENS | Approved | |
| 10/23/2020 | ELECTRIC - FINAL | ESTEVENS | Approved | Approved. |
| 10/23/2020 | ENGINEERING - FINAL | BBENEDON | Approved | Approved. Dick with stover Construction |
| 10/26/2020 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER DISINFECTION REPORT COMPLETED |
| 12/09/2020 | BUILDING - FINAL | RSHERRY | Approved | |
| 12/09/2020 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED |