Permit: T20CM03952
Permit Details
Apply Date:
06/24/2020
Applicant:
Lisa Bowers
Description:
NEW PARKING CANOPIES
Permit Reviews
Permit Number - T20CM03952
Permit Status: Expired
Permit Description: NEW PARKING CANOPIES
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/24/2020 | COMMERCIAL - NEW | 09/30/2020 | COMPLETED |
08/18/2020 | RESUBMITTAL | 09/30/2020 | COMPLETED |
12/01/2020 | RESUBMITTAL | 01/05/2021 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM03952
Permit Status: Expired
Permit Description: NEW PARKING CANOPIES
Total Outstanding Activity Conditions - 5
Date | Name |
---|---|
06/24/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
06/25/2020 | SPECIAL INSPECTION FORMS AND REPORTS REQUIRED PRIOR TO ISSUANCE OF A CERTIFICATE OF OCCUPANCY. |
06/25/2020 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. |
06/25/2020 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. |
06/25/2020 | SPECIAL INSPECTION FOR PILING, DRILLED PIERS AND CAISSONS IS REQUIRED. |
Outstanding Inspections
Permit Status: Expired
Permit Number: T20CM03952
Permite Description: NEW PARKING CANOPIES
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/07/2022 | COT - LCBU - Building Final | N/A | Canceled | Inspection Canceled |
Completed Inspections
Permit Status: Expired
Permit Number: T20CM03952
Permit Description: NEW PARKING CANOPIES
Total Completed Inspections - 6
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/26/2021 | COT - LCBU - Excavation/Rebar/Zoning | Passed | {Activity date: 02/26/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by VLEON1 - APPROVED FOR CAISSON FOOTINGS FOR CANOPIES} ; {Activity date: 02/23/2021; Status: Cancelled; Inspector: DQUINN; Comment: Entered by VLEON1 - CANCELLED PER PM DAN} ; {Activity date: 02/22/2021; Status: Not ready for Inspection; Inspector: TGAUSP; Comment: Entered by VLEON1 - NOT READY CANCELLED BY CONTRACTOR} | |
04/26/2021 | ENGR Engineering Final | Passed | {Activity date: 04/26/2021; Status: Approved; Inspector: MHERNANDEZ; Comment: Entered by VLEON1 - } | |
04/26/2021 | COT - FCON - Fire - Final | Passed | {Activity date: 04/26/2021; Status: Approved; Inspector: CBASALDUA; Comment: Entered by CBASALD1 - } | |
04/30/2021 | COT - LCBU - Framing | Passed | {Activity date: 04/30/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by VLEON1 - } ; {Activity date: 04/29/2021; Status: Not ready for Inspection; Inspector: TGAUSP; Comment: Entered by VLEON1 - NOT READY CANCELLED BY CONTRACTOR} | |
04/30/2021 | COT - LCEL - Electrical Final | Passed | {Activity date: 04/30/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by VLEON1 - } ; {Activity date: 04/26/2021; Status: Cancelled; Inspector: TGAUSP; Comment: Entered by VLEON1 - CANCELLED NOT READY WRONG PERMIT} | |
04/30/2021 | COT - LCBU - Building Progress | Passed | {Activity date: 04/30/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by VLEON1 - } |