Permit: T20CM03401
Permit Details
Apply Date:
06/04/2020
Applicant:
Gregory Moore
Description:
NEW MULTI FAMILY
Permit Reviews
Permit Number - T20CM03401
Permit Status: Complete
Permit Description: NEW MULTI FAMILY
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/14/2021 | RESUBMITTAL | 01/20/2021 | ACTIVE |
06/04/2020 | PLANS OK TO SUBMIT - COMM | 08/05/2020 | COMPLETED |
08/05/2020 | COMMERCIAL - NEW | 11/13/2020 | COMPLETED |
11/06/2020 | RESUBMITTAL | 12/14/2020 | COMPLETED |
11/13/2020 | RESUBMITTAL | 12/08/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM03401
Permit Status: Complete
Permit Description: NEW MULTI FAMILY
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
06/08/2023 | WATER STERILIZATION REPORT IS REQUIRED. |
Conditions
Permit Number - T20CM03401
Permit Status: Complete
Permit Description: NEW MULTI FAMILY
Date | Description | Comments |
---|---|---|
06/04/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T20CM03401
Permite Description: NEW MULTI FAMILY
Total Outstanding Inspections - 9
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | COT - LCEL - Electrical Progress | N/A | Not Ready | |
12/28/2022 | COT - HCBU - Exterior Clips/Sheathing | N/A | Partial Pass | Inspection is for masonry grout for club house at 0’ - 4’. Ok to place grout in progress areas. |
02/27/2023 | COT - LCEL - Construction Power | N/A | Not Ready | |
10/26/2022 | COT - LCPL - Plumbing Final | N/A | Not Ready | |
01/04/2023 | COT - LCPL - Plumbing Progress | N/A | Canceled | |
10/26/2022 | COT - FCON - Fire - Final | N/A | Not Ready | |
07/19/2023 | COT - LCBU - Building Final | N/A | Partial Pass | recommend level 3 TCO |
09/15/2023 | ENGR Engineering Final | N/A | Partial Pass | This site has been Inspected to see what items will need to be addressed before the Development Package can be Approved and placed into Final Status. The Following items have been noted as needing to be addressed prior to this site being allowed to be Closed. A re-inspection of the site will be required once all comments have been addressed. A) Complete the landscaping as shown on the approved plans and provide revised drawings for all changes that have been made to the site since the plans were original approved. B) Complete the grading of all the landscape areas in, around, or adjacent to this site as shown on the approved plans, and ensure that all plant material has been installed accordingly. C) Complete all of the drainage as shown on the Approved plans to ensure that all roof drainage is directed from the down drains into the scuppers out onto the adjacent parking areas. |
09/18/2023 | COT - BULD - SWG Clearance | N/A | Not Applicable |
Completed Inspections
Permit Status: Complete
Permit Number: T20CM03401
Permit Description: NEW MULTI FAMILY
Total Completed Inspections - 36
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/03/2022 | COT - LCPL - Rough Soil | Passed | {Activity date: 05/03/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved for Building #4 (units 4101-4110)} | |
05/03/2022 | COT - LCPL - Sewer | Passed | {Activity date: 05/03/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved for Building #4 (units 4101-4110)} | |
05/03/2022 | COT - LCPL - Backwater Valve | Passed | {Activity date: 05/03/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved for Building #4 (units 4101-4110)} | |
05/11/2022 | COT - LCBU - Building Progress | Passed | {Activity date: 05/11/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP. Top out of eight foot site wall sections.} ; {Activity date: 04/29/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by VVERA1 - Partial for remaining 1st lift of the perimeter wall continuing at the north and west property lines (west of building 1 and 2), okay to grout progress areas} ; {Activity date: 04/26/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - - Partial for 1st lift of the perimeter wall at the north property line (behind building 4)} ; {Activity date: 03/31/2022; Status: Not ready for Inspection; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - NR} ; {Activity date: 10/25/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, construction meeting no inspection required.} | |
05/31/2022 | COT - LCEL - Electrical Underground | Passed | {Activity date: 05/31/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved} | |
05/31/2022 | COT - LCBU - Excavation/Rebar/Zoning | Passed | {Activity date: 05/31/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved} ; {Activity date: 03/31/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Partial approval for foundations of the site walls (8’ high) at the North and West property lines, okay to pour progress areas} | |
05/31/2022 | COT - LCBU - Preslab | Passed | {Activity date: 05/31/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved} [approved on preslab, rebar, and electric underground for club house/laundry room/well room] Carrazco 11-08-22 |
|
05/31/2022 | COT - LCEL - Grounding/Bonding | Passed | {Activity date: 05/31/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved} | |
08/25/2022 | COT - LCBU - Exterior Clips/Sheathing | Passed | {Activity date: 08/25/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. Ok to cover exterior walls. } ; {Activity date: 08/24/2022; Status: Cancelled; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - ) cancel per Tom. Contractor} |
|
08/25/2022 | COT - LCBU - Roof Nailing | Passed | {Activity date: 08/25/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. Ok to dry in roof system.} ; {Activity date: 08/24/2022; Status: Not ready for Inspection; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - not ready. Need access to roof.} | |
11/09/2022 | COT - LCPL - Yard Water Line | Passed | ||
12/15/2022 | COT - LCPL - Plumbing Above Ceiling | Passed | ||
12/15/2022 | COT - LCBU - Framing | Passed | ||
12/15/2022 | COT - LCME - Mechanical Intermediate | Passed | ||
12/15/2022 | COT - LCBU - Building Above Ceiling | Passed | ||
12/15/2022 | COT - LCBU - Firewall/Fire Barrier/Firestop | Passed | ||
12/15/2022 | COT - LCEL - Electrical Above Ceiling | Passed | ||
12/15/2022 | COT - LCME - Mechanical Above Ceiling | Passed | ||
12/15/2022 | COT - HCBU - Interior Shear Bracing | Passed | ||
12/15/2022 | COT - LCPL - Plumbing Intermediate | Passed | ||
01/10/2023 | COT - HCBU - Masonry Pregrout | Passed | ||
02/08/2023 | COT - HCBU - Exterior Clips/Sheathing | Passed | for club house only | |
02/08/2023 | COT - HCBU - Roof Nailing | Passed | for clubhouse only | |
03/06/2023 | COT - LCEL - Construction Power | Passed | ECO Clearance to TEP for construction power at Bldg 4 (units #4101, 4102, 4103, 4104, 4105, 4106, 4107, 4108, 4109, 4110) | |
07/19/2023 | COT - LCPL - Plumbing Final | Passed | ||
07/19/2023 | COT - LCPL - Plumbing Progress | Passed | ||
07/19/2023 | COT - LCBU - Sustainability | Passed | ||
07/19/2023 | COT - LCEL - Electrical Final | Passed | ||
07/19/2023 | COT - LCME - Mechanical Final | Passed | ||
07/19/2023 | COT - LCEL - Electrical Intermediate | Passed | ||
07/19/2023 | COT - LCEL - Outdoor Lighting | Passed | ||
07/19/2023 | COT - FCON - Fire - Final | Passed | ||
07/19/2023 | COT - LCME - Mechanical Progress | Passed | ||
09/15/2023 | COT - LCBU - Building Final | Passed | ||
09/18/2023 | COT - LCBU - CofO | Passed | 9/18/23: CofO | |
09/18/2023 | BULD - Electrical Clearance | Passed |