Start Date Submittal Complete Date Status  
04/28/2020 COMMERCIAL - TI 06/01/2020 COMPLETED Review Details
06/01/2020 RESUBMITTAL 06/12/2020 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T20CM02635
Permit Status: Expired
Permit Description: TI: RETAIL
Total Outstanding Activity Conditions - 1
Date Name
04/28/2020 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Outstanding Inspections

Permit Status: Expired
Permit Number: T20CM02635
Permite Description: TI: RETAIL
Total Outstanding Inspections - 2
Last Inspection Date Description Inspector Results Comments
12/11/2020 COT - LCME - Mechanical Intermediate N/A Canceled {Activity date: 12/11/2020; Status: Not Applicable; Inspector: TTREMBULAK; Comment: Entered by PAHUMAD1 - Not applicable.
}
12/11/2020 COT - LCBU - CofO N/A Complete (Recurring) {Activity date: 12/11/2020; Status: Continued; Inspector: TTREMBULAK; Comment: Entered by PAHUMAD1 - Cancelled, pending other inspections.}

Completed Inspections

Permit Status: Expired
Permit Number: T20CM02635
Permit Description: TI: RETAIL
Total Completed Inspections - 14
Date Description Inspector Results Comments
10/14/2020 COT - LCPL - Plumbing Intermediate Passed {Activity date: 10/14/2020; Status: Approved; Inspector: ESTEVENS; Comment: Entered by RSALDAT1 - Approved} ; {Activity date: 10/09/2020; Status: Denied; Inspector: TTREMBULAK; Comment: Entered by JSCHNEI2 - Denied. No contact information given.
}
10/16/2020 COT - LCPL - Rough Soil Passed {Activity date: 10/16/2020; Status: Approved; Inspector: ESTEVENS; Comment: Entered by JSCHNEI2 - . Approved

} ; {Activity date: 10/14/2020; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by RSALDAT1 - Partial. Floor sink has S-trap, sink directional fitting is in backward.

} ; {Activity date: 10/09/2020; Status: Denied; Inspector: TTREMBULAK; Comment: Entered by JSCHNEI2 - Denied. No contact information given.}
12/11/2020 COT - LCBU - Building Above Ceiling Passed {Activity date: 12/11/2020; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by PAHUMAD1 - }
12/11/2020 COT - LCEL - Electrical Intermediate Passed {Activity date: 12/11/2020; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by PAHUMAD1 - }
12/11/2020 COT - LCBU - Framing Passed {Activity date: 12/11/2020; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by PAHUMAD1 - }
12/11/2020 COT - LCEL - Electrical Final Passed {Activity date: 12/11/2020; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by PAHUMAD1 - }
12/11/2020 ENGR Engineering Final Passed {Activity date: 12/11/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by PAHUMAD1 - Approved. Gerry. Has finished all the work and removed all construction materials and debris as required}
12/11/2020 COT - FCON - Fire - Final Passed {Activity date: 12/11/2020; Status: Approved; Inspector: wmotto1; Comment: Entered by WMOTTO1 - }
12/11/2020 COT - LCEL - Electrical Above Ceiling Passed {Activity date: 12/11/2020; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by PAHUMAD1 - }
12/11/2020 COT - LCBU - Building Progress Passed {Activity date: 12/11/2020; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by PAHUMAD1 - }
02/01/2021 COT - LCME - Mechanical Final Passed {Activity date: 02/01/2021; Status: Approved; Inspector: RSHERRY; Comment: Entered by RSHERRY1 - REVIEW OF AIR BALANCE REPORT COMPLETED} ; {Activity date: 12/11/2020; Status: Partial Approval; Inspector: TTREMBULAK; Comment: Entered by PAHUMAD1 - Partial, pending air balance report.
} ; {Activity date: 05/05/2020; Status: Prior to Final Inspectn; Inspector: RSHERRY; Comment: Entered by RSHERRY1 - AIR BALANCE REPORT REQUIRED}
02/01/2021 COT - LCPL - Plumbing Final Passed {Activity date: 02/01/2021; Status: Approved; Inspector: RSHERRY; Comment: Entered by RSHERRY1 - REVIEW OF WATER DISINFECTION REPORT COMPLETED} ; {Activity date: 12/11/2020; Status: Partial Approval; Inspector: TTREMBULAK; Comment: Entered by PAHUMAD1 - Partial, pending water disinfection report.
} ; {Activity date: 06/02/2020; Status: Prior to Final Inspectn; Inspector: RSHERRY; Comment: Entered by RSHERRY1 - WATER DISINFECTION REPORT REQUIRED}
02/11/2021 COT - LCBU - Building Final Passed {Activity date: 02/11/2021; Status: Approved; Inspector: RSHERRY; Comment: Entered by RSHERRY1 - } ; {Activity date: 12/11/2020; Status: Partial Approval; Inspector: TTREMBULAK; Comment: Entered by PAHUMAD1 - Partial, pending other inspections.}
02/11/2021 COT - ENGR - Site - Assurance Release Passed {Activity date: 02/11/2021; Status: Approved; Inspector: RSHERRY; Comment: Entered by RSHERRY1 - HEALTH DEPT FINAL INSPECTION APPROVED BY CHRISTPHER SHETTERLY 2/10/21}

Documents

File Name Document Type  
1_PERMIT_APPLICATION.PDF DOCUMENTS VIEW
2_PERMIT_T20CM02635_-_PERMIT REVIEW DETAILS.PDF DOCUMENTS VIEW
2_STRUCTURAL_CALCULATIONS.PDF DOCUMENTS VIEW
2_PLAN_SET.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW