Permit Details

Status:
Complete
Type:
Commercial Building
Apply Date:
04/20/2020
Applicant:
Albert LeCocq
Description:
NEW APARTMENT BUILDING

Permit Reviews

Permit Number - T20CM02426
Permit Status: Complete
Permit Description: NEW APARTMENT BUILDING
Start Date Submittal Complete Date Status  
04/20/2020 PLANS OK TO SUBMIT - COMM 12/01/2020 COMPLETED Review Details
04/29/2020 3RD PARTY REVIEW - COMMERCIAL 06/17/2020 COMPLETED Review Details
06/17/2020 3RD PARTY REVIEW - COMMERCIAL 06/24/2020 COMPLETED Review Details
06/24/2020 3RD PARTY REVIEW - COMMERCIAL 07/20/2020 COMPLETED Review Details
12/01/2020 3RD PARTY REVIEW - REVISION/OTHER 01/14/2021 COMPLETED Review Details
06/13/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 06/17/2024 APPROVED Review Details

Conditions

Permit Number - T20CM02426
Permit Status: Complete
Permit Description: NEW APARTMENT BUILDING
Date Description Comments
04/20/2020 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
03/15/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
03/15/2024 SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: T20CM02426
Permite Description: NEW APARTMENT BUILDING
Total Outstanding Inspections - 3
Last Inspection Date Description Inspector Results Comments
10/12/2021 COT - LCBU - Building Above Ceiling N/A Not Applicable {Activity date: 10/12/2021; Status: Not Applicable; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - 1036 (BUILDING ABOVE CEILING) -NA
07/02/2021 1030 RELEFANTE ROOF NAILING Approve
07/02/2021 1035 RELEFANTE FRAMING Approved.}
10/26/2022 COT - FCON - Fire - Final N/A Not Ready
10/26/2022 COT - HCBU - Interior Shear Bracing N/A Not Ready

Completed Inspections

Permit Status: Complete
Permit Number: T20CM02426
Permit Description: NEW APARTMENT BUILDING
Total Completed Inspections - 23
Date Description Inspector Results Comments
02/03/2021 COT - LCPL - Plumbing Intermediate Passed {Activity date: 02/03/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by VLEON1 - 1st floor apartments #5, #6, #7, #8 are Approved
Water and DWV not on test in 2nd floor apartments #9, #10, #11, #12, #13, #14, #15, #16 Not Ready (NR)} ; {Activity date: 01/22/2021; Status: Partial Approval; Inspector: JBURGE; Comment: Entered by VLEON1 - Partial. Apartments #1; 2; 3; 4. Ok to insulate and cover walls.}
02/05/2021 COT - LCEL - Electrical Intermediate Passed {Activity date: 02/05/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - is Approved} ; {Activity date: 02/03/2021; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by VLEON1 - Partial Approval for #5, #6, #7, #8, #9, #10, #11, #12, #13, #14, #15, #16
Verify missing receptacles at final, surface mounted receptacles in bedrooms and living rooms} ; {Activity date: 01/22/2021; Status: Partial Approval; Inspector: JBURGE; Comment: Entered by VLEON1 - Partial. Apartments #1; 2; 3; 4. Ok to insulate and cover walls.}
03/31/2021 COT - LCPL - Rough Soil Passed {Activity date: 03/31/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by VLEON1 - Approved for 20 units within Building #4, soil will connect to existing 6” line}
04/14/2021 COT - LCBU - Excavation/Rebar/Zoning Passed {Activity date: 04/14/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by VLEON1 - }
04/14/2021 COT - LCBU - Preslab Passed {Activity date: 04/14/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by VLEON1 - }
04/14/2021 COT - LCEL - Grounding/Bonding Passed {Activity date: 04/14/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by VLEON1 - }
07/02/2021 COT - LCBU - Framing Passed {Activity date: 07/02/2021; Status: Approved; Inspector: RELEFATNE; Comment: Entered by RSALDAT1 - is Approved}
07/02/2021 COT - LCBU - Roof Nailing Passed {Activity date: 07/02/2021; Status: Approved; Inspector: RELEFANTE; Comment: Entered by RSALDAT1 - }
08/16/2021 COT - HCBU - Exterior Clips/Sheathing Passed {Activity date: 08/16/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - Approved}
05/17/2022 PDSD Building Division - TEP PM Clearance Passed {Activity date: 05/17/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - CODE ECO FOR OWNERS PANEL} ; {Activity date: 12/09/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - CODE INCR ok to release following meters. ( East House Panel, West House Panel, 41, 42, 43, 44, 45, 46, 47, 48, 49, 50, 51, 52, 53, 54, 55, 56, 57, 58, 59, 60)}
05/17/2022 COT - LCEL - Construction Power Passed {Activity date: 05/17/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved, Clear TEP ECO for (Owners panel)}
05/20/2022 COT - LCBU - Building Final Passed {Activity date: 05/20/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved. Building #4.}
05/20/2022 COT - LCEL - Electrical Underground Passed {Activity date: 05/20/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved 2090}
05/20/2022 COT - LCME - Mechanical Final Passed {Activity date: 05/20/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved. Building #4.}
05/20/2022 COT - LCBU - Firewall/Fire Barrier/Firestop Passed {Activity date: 05/20/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved 1090}
05/20/2022 COT - LCEL - Electrical Final Passed {Activity date: 05/20/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved. Building #4.}
05/20/2022 COT - LCME - Mechanical Intermediate Passed {Activity date: 05/20/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved 4090} ; {Activity date: 02/03/2021; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by VLEON1 - Partial Approval for #5, #6, #7, #8, #9, #10, #11, #12, #13, #14, #15, #16} ; {Activity date: 01/22/2021; Status: Partial Approval; Inspector: JBURGE; Comment: Entered by VLEON1 - Partial. Apartments #1; 2; 3; 4. Ok to insulate and cover walls.}
05/20/2022 COT - LCEL - Service Upgrade Passed {Activity date: 05/20/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved 2090} ; {Activity date: 12/09/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 -
5/12/22: INSPECTOR DM CHANGED AP TO PA TO ALLOW OWNER TO CALL IN FOR NEW INSPECTION ASSOCIATED WITH OWN4.

APPROVED Clear TEP INCR ok to release following meters. ( East House Panel, West House Panel, 41, 42, 43, 44, 45, 46, 47, 48, 49, 50, 51, 52, 53, 54, 55, 56, 57, 58, 59, 60)}
05/20/2022 COT - LCPL - Plumbing Final Passed {Activity date: 05/20/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved. Building #4.}
06/13/2022 COT - FCON - Alarm - Final Passed {Activity date: 06/13/2022; Status: Approved; Inspector: CBASALDUA; Comment: Entered by CBASALD1 - Alarm test completed by J. Fordney.}
06/13/2022 COT - FCON - Sprinkler - Final Passed {Activity date: 06/13/2022; Status: Approved; Inspector: CBASALDUA; Comment: Entered by CBASALD1 - }
03/01/2024 COT - FCON - Fire - Final Passed
03/01/2024 COT - HCBU - Interior Shear Bracing Passed

Documents

File Name Document Type  
COFO_FINALCOFO_COMMERCIAL.PDF DOCUMENTS VIEW
SCAN_MAREVAL1_2024-06-12-11-35-47-2024-06-12_V1.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
FEE SHEET.PDF DOCUMENTS VIEW
COMPLIANCE CERT .PDF DOCUMENTS VIEW
CHECKLIST.PDF DOCUMENTS VIEW
APPROVAL LETTER.PDF DOCUMENTS VIEW
HVAC LOAD CALCS.PDF DOCUMENTS VIEW
SIGNED PSA.PDF DOCUMENTS VIEW
PLAN.PDF CONSTRPLANS VIEW
PERMIT.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
SPECIAL INSPECTION CERT DOCUMENTS VIEW
STRUCTURAL CALCS DOCUMENTS VIEW
PLAN SET CONSTRPLANS VIEW
REV_PLAN SET.PDF CONSTRPLANS VIEW