Permit Details

Status:
L of c
Type:
COMMERCIAL ALTERATION
Apply Date:
04/13/2020
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
W-TI: CATH LAB MAIN HOSPITAL BLDG
Architects:
  • BOLLARD, MARK EDWARD

Permit Reviews

Permit Number - T20CM02224
Permit Status: L of c
Permit Description: W-TI: CATH LAB MAIN HOSPITAL BLDG
Start Date Submittal Complete Date Status  
04/13/2020 COMMERCIAL - TI 06/03/2020 COMPLETED Review Details
06/03/2020 RESUBMITTAL 07/27/2020 COMPLETED Review Details
08/06/2020 RESUBMITTAL 10/07/2020 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T20CM02224
Permit Status: L of c
Permit Description: W-TI: CATH LAB MAIN HOSPITAL BLDG
Total Outstanding Activity Conditions - 1
Date Name
04/13/2020 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: L of c
Permit Number: T20CM02224
Permit Description: W-TI: CATH LAB MAIN HOSPITAL BLDG
Total Completed Inspections - 24
Date Description Inspector Results Comments
08/13/2020 PLUMBING - FINAL RSHERRY Approved WATER DISINFECTION REPORT REQUIRED
03/30/2021 PLUMBING - ROUGH, SOIL DQUINN Approved APPROVED - From existing toilet to new sink ok to backfill.
05/05/2021 PLUMBING - INTERMEDIATE TGAUSP Approved
05/05/2021 BUILDING PRE-SLAB TGAUSP Approved
05/05/2021 EXCAVATION/LAYOUT REBAR & ZON TGAUSP Approved
05/11/2021 MECHANICAL - INTERMEDIATE DQUINN Approved APPROVED Main trunks ok to insulate and laterals and boots ok to land in lids.
05/28/2021 PLUMBING - ABOVE CEILING DQUINN Approved
05/28/2021 FIREWALL/FIREBARRIER/FIRESTOP DQUINN Approved
06/02/2021 ELECTRIC - ABOVE CEILING TGAUSP Approved APPROVED OK TO COVER
06/02/2021 ELECTRIC - INTERMEDIATE TGAUSP Approved APPROVED OK TO COVER
06/02/2021 PLUMBING - MD GAS/PRECONST MTG TGAUSP Approved Approved, spoke to Raul regarding required inspection reports
06/03/2021 PLUMBING - MEDICAL GAS/TEST ESTEVENS Approved Approved by third party company. MTA in Phoenix.
06/03/2021 FRAMING ESTEVENS Approved
06/03/2021 MECHANICAL - HYDRONIC PIPING ESTEVENS Approved Approved. New VAV unit in cath lab roof maintenance room to existing plumbing in cath lab. New VAV in control room connected to existing plumbing.
06/23/2021 BUILDING ABOVE CEILING DQUINN Approved Elec and building above ceiling ok in cath lab control room.
06/30/2021 FIRE - FINAL MRoss Approved
06/30/2021 FIRE - ALARM FINAL MRoss Approved
06/30/2021 FIRE SPKLR - FINAL MRoss Approved
06/30/2021 ELECTRIC - FINAL DQUINN Approved
07/02/2021 ENGINEERING - FINAL BBENEDON Approved
07/08/2021 BUILDING - PROGRESS DQUINN Approved Ap
07/08/2021 BUILDING - FINAL DQUINN Approved Ap
07/08/2021 PLUMBING - MEDICAL GAS/FINAL DQUINN Approved Ap
07/08/2021 MECHANICAL - FINAL DQUINN Approved All requirements complete for occupancy.