Apply Date:
04/13/2020
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
W-TI: CATH LAB MAIN HOSPITAL BLDG
Architects:
- BOLLARD, MARK EDWARD
Permit Reviews
Permit Number - T20CM02224
Permit Status: L of c
Permit Description: W-TI: CATH LAB MAIN HOSPITAL BLDG
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/13/2020 | COMMERCIAL - TI | 06/03/2020 | COMPLETED |
06/03/2020 | RESUBMITTAL | 07/27/2020 | COMPLETED |
08/06/2020 | RESUBMITTAL | 10/07/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM02224
Permit Status: L of c
Permit Description: W-TI: CATH LAB MAIN HOSPITAL BLDG
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
04/13/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T20CM02224
Permit Description: W-TI: CATH LAB MAIN HOSPITAL BLDG
Total Completed Inspections - 24
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/13/2020 | PLUMBING - FINAL | RSHERRY | Approved | WATER DISINFECTION REPORT REQUIRED |
03/30/2021 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | APPROVED - From existing toilet to new sink ok to backfill. |
05/05/2021 | PLUMBING - INTERMEDIATE | TGAUSP | Approved | |
05/05/2021 | BUILDING PRE-SLAB | TGAUSP | Approved | |
05/05/2021 | EXCAVATION/LAYOUT REBAR & ZON | TGAUSP | Approved | |
05/11/2021 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | APPROVED Main trunks ok to insulate and laterals and boots ok to land in lids. |
05/28/2021 | PLUMBING - ABOVE CEILING | DQUINN | Approved | |
05/28/2021 | FIREWALL/FIREBARRIER/FIRESTOP | DQUINN | Approved | |
06/02/2021 | ELECTRIC - ABOVE CEILING | TGAUSP | Approved | APPROVED OK TO COVER |
06/02/2021 | ELECTRIC - INTERMEDIATE | TGAUSP | Approved | APPROVED OK TO COVER |
06/02/2021 | PLUMBING - MD GAS/PRECONST MTG | TGAUSP | Approved | Approved, spoke to Raul regarding required inspection reports |
06/03/2021 | PLUMBING - MEDICAL GAS/TEST | ESTEVENS | Approved | Approved by third party company. MTA in Phoenix. |
06/03/2021 | FRAMING | ESTEVENS | Approved | |
06/03/2021 | MECHANICAL - HYDRONIC PIPING | ESTEVENS | Approved | Approved. New VAV unit in cath lab roof maintenance room to existing plumbing in cath lab. New VAV in control room connected to existing plumbing. |
06/23/2021 | BUILDING ABOVE CEILING | DQUINN | Approved | Elec and building above ceiling ok in cath lab control room. |
06/30/2021 | FIRE - FINAL | MRoss | Approved | |
06/30/2021 | FIRE - ALARM FINAL | MRoss | Approved | |
06/30/2021 | FIRE SPKLR - FINAL | MRoss | Approved | |
06/30/2021 | ELECTRIC - FINAL | DQUINN | Approved | |
07/02/2021 | ENGINEERING - FINAL | BBENEDON | Approved | |
07/08/2021 | BUILDING - PROGRESS | DQUINN | Approved | Ap |
07/08/2021 | BUILDING - FINAL | DQUINN | Approved | Ap |
07/08/2021 | PLUMBING - MEDICAL GAS/FINAL | DQUINN | Approved | Ap |
07/08/2021 | MECHANICAL - FINAL | DQUINN | Approved | All requirements complete for occupancy. |