Permit: T20CM00821
Permit Details
Apply Date:
02/04/2020
Applicant:
VENEZIANO, PHILIP JOHN
Description:
TI: STORAGE
Architects:
- VENEZIANO, PHILIP JOHN
Contractors:
- WENTZ AND PATRICK CONSTRUCTION C
Permit Reviews
Permit Number - T20CM00821
Permit Status: C of o
Permit Description: TI: STORAGE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/04/2020 | PLANS OK TO SUBMIT - COMM | 02/06/2020 | COMPLETED |
| 02/06/2020 | COMMERCIAL - TI | 07/13/2020 | COMPLETED |
| 07/13/2020 | RESUBMITTAL - TI ALL | 08/27/2020 | COMPLETED |
| 09/04/2020 | RESUBMITTAL | 10/01/2020 | COMPLETED |
| 10/01/2020 | RESUBMITTAL | 11/17/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM00821
Permit Status: C of o
Permit Description: TI: STORAGE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 02/04/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T20CM00821
Permit Description: TI: STORAGE
Total Completed Inspections - 27
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/29/2020 | MECHANICAL - FINAL | RSHERRY | Approved | AIR BALANCE REPORT REQUIRED |
| 10/02/2020 | EXCAVATION/LAYOUT REBAR & ZON | BSTEVENS | Approved | OK to pour footings pending plan review approval. |
| 10/15/2020 | STEM WALL/RETAINING WALL | BSTEVENS | Approved | OK to grout to 4 foot level. |
| 11/30/2020 | BUILDING PRE-SLAB | ESTEVENS | Approved | |
| 12/17/2020 | REINFORCED MASONRY PRE-GROUT | DQUINN | Approved | S., E., and N. Walls ok to grout to top at 17’4” |
| 02/05/2021 | ROOF NAILING | DQUINN | Approved | APPROVED |
| 02/26/2021 | PLUMBING - ROOF DRAINS | DQUINN | Approved | APPROVED |
| 02/26/2021 | FRAMING | DQUINN | Approved | APPROVED METAL SHEAR WALLS OK TO ROCK |
| 03/19/2021 | TEP CLEARANCE - PM | DQUINN | Approved | CODE INCR/UNITS M S |
| 03/19/2021 | ELECTRIC - SERVICE UPGRADE | DQUINN | Approved | |
| 04/02/2021 | ELECTRIC - ABOVE CEILING | DQUINN | Approved | Ap |
| 04/02/2021 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | Ap |
| 04/05/2021 | FIRE - FINAL | CBASALDUA | Approved | |
| 07/16/2021 | BUILDING - FINAL | DQUINN | Approved | SPEC. INSPECTION AP |
| 07/16/2021 | BUILDING - FINAL | DQUINN | Approved | SPECIAL INSPECTIONS LACKING: Ap Close permit and ok for C of O |
| 07/16/2021 | BUILDING - PROGRESS | DQUINN | Approved | Ap |
| 07/16/2021 | CERTIFICATE OF OCCUPANCY | DQUINN | Approved | Ap |
| 07/16/2021 | STUCCO MESH | DQUINN | Approved | Ap |
| 07/16/2021 | U VALUE FOR WINDOW | DQUINN | Approved | Ap |
| 07/16/2021 | BUILDING ABOVE CEILING | DQUINN | Approved | Ap |
| 07/16/2021 | EXT METAL CLIPS/EXT SHEATHING | DQUINN | Approved | Ap |
| 07/16/2021 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | Ap |
| 07/16/2021 | PLUMBING - FINAL | DQUINN | Approved | |
| 07/16/2021 | ELECTRIC - FINAL | DQUINN | Approved | Ap |
| 07/16/2021 | ELECTRIC - OUTDOOR LIGHTING | DQUINN | Approved | Ap |
| 07/16/2021 | OUTDOOR LIGHTING FINAL | DQUINN | Approved | Ap |
| 07/16/2021 | ENGINEERING - FINAL | BBENEDON | Approved | Approved |