Permit Details

Status:
Final
Type:
Barricade Only
Address:
4798 N 1ST AV
Address NEW:
4798 N 1ST AV
Apply Date:
10/09/2019
Applicant:
COX COMMUNICATIONS
Description:
Original Permit-T19RW02786- Start Point: From the COX ped on the NW corner of 4502 N 1st Ave, begin 312' pull through existing conduit heading North, continue 118' pull through heading West. 353' pull through heading North , continue pull through, West 35' to out of ROW NOTES: AS THE CONTRACTOR, YOU MUST FOLLOW THE RUNNING LINE SUBMITTED TO THE CITY, IF DEVIATED, A REVISION MUST BE SUBMITTED AND APPROVED BEFORE CONTINUING WORK. 1 St is under a pavement moratorium, any new asphalt that is disturbed will require a 2" mill and overlay for 50' in each direction from the outside of the cut for all effected travel lanes.
Contractors:
  • MEARS GROUP INC *** APA ***
  • SOUTHWEST BARRICADES LLC
  • TRUENET COMMUNICATIONS CORP

Completed Inspections

Permit Status: Final
Permit Number: T19RW05961
Permit Description: Original Permit-T19RW02786- Start Point: From the COX ped on the NW corner of 4502 N 1st Ave, begin 312' pull through existing conduit heading North, continue 118' pull through heading West. 353' pull through heading North , continue pull through, West 35' to out of ROW NOTES: AS THE CONTRACTOR, YOU MUST FOLLOW THE RUNNING LINE SUBMITTED TO THE CITY, IF DEVIATED, A REVISION MUST BE SUBMITTED AND APPROVED BEFORE CONTINUING WORK. 1 St is under a pavement moratorium, any new asphalt that is disturbed will require a 2" mill and overlay for 50' in each direction from the outside of the cut for all effected travel lanes.
Total Completed Inspections - 1
Date Description Inspector Results Comments
02/28/2020 TDOT-EXCAV GENERAL INSPECTION A.Gomez Approved Communication work completed, observed no damage to existing sidewalk, or asphalt.