Permit: T19RW03547
Permit Details
Apply Date:
06/20/2019
Applicant:
N/A
Description:
SIDEWALK REMOVAL/REPLACEMENT, WATERLINE, FIRELINE, STORN DRAIN AND SEWER INSTALL, AC REMOVAL/INSTALL, 2 DRIVEWAY APRONS, CURBS, 4 CURB ACCESS RAMPS, POTHOLING, ALL PER DP19-0038 7/8/19 WORK DESCRIPTION CHANGE: CUSHING ST LANE CLOSURE WEST BOUND TO LOCATE STORM DRAIN AT 13' -6 BFG (BELOW FINISH GRADE). THE EAST BOUND LANE WILL REMAIN OPEN WITH FLAGMEN TO DIRECT TRAFFIC WHILE THE WORK IS BEING PERFORMED. 10/24/2019 - WET UTILITES OFFSITE ON CUSHING STREET NOTES: PERMIT END DATE HAS BEEN MODIFIED DUE TO HOLIDAY RESTRICTION BEGINNING NOVEMBER 28TH 2019 - JANUARY 2ND 2020. 10/31/19 - TRAFFIC CONTROL PLAN CHANGE - FULL ROAD CLOSURE REQUIRED FOR STORM DRAIN AND SEWER INSTALLATION AND AC REMOVAL/INSTALL. WORK SHALL BE COMPLETED WHEN READY TO INSTALL FIRELINE AND DOMESTIC WATER TAPS, FULL LANE CLOSURE WILL NOT BE REQUIRED, THE USE OF FLAGMEN WILL BE USED, HOWEVER, A NEW TRAFFIC CONTROL PLAN CHANGE FORM SHALL BE SUBMITTED FOR REVIEW. WORKING HOURS SHALL BE MONDAY - FRIDAY FROM 7:00 AM TO 4:00 PM. BUS STOP IN THE AREA, CONTACT SUN TRAN, BEA PAULUS AT 520-206-8826 AND/OR CHRISTINA ROCK AT 520-206-8934 FOR COORDINATION.
Contractors:
- EAGLE ROCK EXCAVATING L L C
- RYAN COMPANIES US, INC.
- STURGEON ELECTRIC COMPANY *APA*
Completed Inspections
Permit Status: Final
Permit Number: T19RW03547
Permit Description: SIDEWALK REMOVAL/REPLACEMENT, WATERLINE, FIRELINE, STORN DRAIN AND SEWER INSTALL, AC REMOVAL/INSTALL, 2 DRIVEWAY APRONS, CURBS, 4 CURB ACCESS RAMPS, POTHOLING, ALL PER DP19-0038
7/8/19 WORK DESCRIPTION CHANGE:
CUSHING ST LANE CLOSURE WEST BOUND TO LOCATE STORM DRAIN AT 13' -6 BFG (BELOW FINISH GRADE). THE EAST BOUND LANE WILL REMAIN OPEN WITH FLAGMEN TO DIRECT TRAFFIC WHILE THE WORK IS BEING PERFORMED.
10/24/2019 - WET UTILITES OFFSITE ON CUSHING STREET
NOTES:
PERMIT END DATE HAS BEEN MODIFIED DUE TO HOLIDAY RESTRICTION BEGINNING NOVEMBER 28TH 2019 - JANUARY 2ND 2020.
10/31/19 - TRAFFIC CONTROL PLAN CHANGE - FULL ROAD CLOSURE REQUIRED FOR STORM DRAIN AND SEWER INSTALLATION AND AC REMOVAL/INSTALL. WORK SHALL BE COMPLETED
WHEN READY TO INSTALL FIRELINE AND DOMESTIC WATER TAPS, FULL LANE CLOSURE WILL NOT BE REQUIRED, THE USE OF FLAGMEN WILL BE USED, HOWEVER, A NEW TRAFFIC CONTROL PLAN CHANGE FORM SHALL BE SUBMITTED FOR REVIEW.
WORKING HOURS SHALL BE MONDAY - FRIDAY FROM 7:00 AM TO 4:00 PM.
BUS STOP IN THE AREA, CONTACT SUN TRAN, BEA PAULUS AT 520-206-8826 AND/OR CHRISTINA ROCK AT 520-206-8934 FOR COORDINATION.
Total Completed Inspections - 1
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/28/2019 | TDOT-EXCAV GENERAL INSPECTION | Bravin | Approved | potholing on cushing. No more work until traffic issues resolved |