Permit: T19RW01208
Permit Details
Apply Date:
03/07/2019
Applicant:
K E & G CONSTRUCTION ***APA***
Description:
Sewer Rehabilitation between MH 9918-16 and MH 5766-12; remove approximately 22 LF of 8" ACP and replace with 22 LF of 8" PVC and CIPP lining between MH 9918-16 and MH 5766-12. 04/26/2019-PLAN CHANGE EDIT EXISTING PERMIT; CHANGE TRAFFIC TIMES TO 6AM-6PM FROM 6PM TO 6AM-SEWER REHABILATION-CIPP LINING BETWEEN MH9918-16 AND MH5766-12
Contractors:
- BORDER TRAFFIC SAFETY LLC
- INSITUFORM TECHNOLOGIES LLC
- PROPIPE PLUMBING AND ROOTER L L C
Completed Inspections
Permit Status: Final
Permit Number: T19RW01208
Permit Description: Sewer Rehabilitation between MH 9918-16 and MH 5766-12; remove approximately 22 LF of 8" ACP and replace with 22 LF of 8" PVC and CIPP lining between MH 9918-16 and MH 5766-12.
04/26/2019-PLAN CHANGE
EDIT EXISTING PERMIT; CHANGE TRAFFIC TIMES TO 6AM-6PM FROM
6PM TO 6AM-SEWER REHABILATION-CIPP LINING BETWEEN
MH9918-16 AND MH5766-12
Total Completed Inspections - 1
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/08/2019 | TDOT-EXCAV GENERAL INSPECTION | Bravin | Approved | roadway was milled on 5/7 at a depth of 2 inches area was repaved due to moritorium on 5/8/19 . Area is approved and job is complete |