Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T19RW01124
Permit Details
Apply Date:
03/04/2019
Applicant:
N/A
Description:
Install 397 feet of steel gas line along Broadway east of Country Club. Replace 4,421 feet of plastic gas line crossing Broadway at Park, Cherry, and Campbell and along Broadway from 2707 E Broadway to 2955 E Broadway. Replace 1,637 feet of plastic service line. SWG/NPL WILL WORK MONDAY - SATURDAY
Contractors:
- NORTHERN PIPELINE CONSTRUCTION CO
Completed Inspections
Permit Status: Final
Permit Number: T19RW01124
Permit Description: Install 397 feet of steel gas line along Broadway east of Country Club. Replace 4,421 feet of plastic gas line crossing Broadway at Park, Cherry, and Campbell and along Broadway from 2707 E Broadway to 2955 E Broadway. Replace 1,637 feet of plastic service line.
SWG/NPL WILL WORK MONDAY - SATURDAY
Total Completed Inspections - 1
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/22/2019 | TDOT-EXCAV GENERAL INSPECTION | Bravin | Approved | 5/13/2019 Gas line project started. Mike Graham was notifified throughout the project to keep the city updated on progress. All new gas line was installed and backfilled with slurry material per my request. Adrian was the foreman 940-6337 from APL. Adrian continously contacted me for any issues. All patching and concrete was approved. No issues with project and teamwork between the city and APL made this project smooth for the traveling public |