Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date |
Description |
Inspector |
Results |
Comments |
| 07/22/2019 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
5/13/2019 Gas line project started. Mike Graham was notifified throughout the project to keep the city updated on progress. All new gas line was installed and backfilled with slurry material per my request. Adrian was the foreman 940-6337 from APL. Adrian continously contacted me for any issues. All patching and concrete was approved. No issues with project and teamwork between the city and APL made this project smooth for the traveling public |