Permit: T19CM09462
Permit Details
Apply Date:
12/30/2019
Applicant:
CYRUS MOORE
Description:
NEW SFR
Permit Reviews
Permit Number - T19CM09462
Permit Status: Final
Permit Description: NEW SFR
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/21/2020 | 3RD PARTY REVIEW - RESIDENTIAL | 11/13/2020 | COMPLETED |
| 12/30/2019 | PLANS OK TO SUBMIT - RES | 12/30/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM09462
Permit Status: Final
Permit Description: NEW SFR
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 12/30/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T19CM09462
Permit Description: NEW SFR
Total Completed Inspections - 22
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/01/2020 | PLUMBING - ROUGH, SOIL | JBURGE | Approved | . Approved. Ok to cover progress areas. |
| 12/16/2020 | ELECTRIC - UNDERGROUND | DQUINN | Approved | APPROVED |
| 12/16/2020 | ELECTRIC - UFER | DQUINN | Approved | APPROVED |
| 12/16/2020 | BUILDING PRE-SLAB | DQUINN | Approved | APPROVED |
| 12/16/2020 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | APPROVED |
| 12/16/2020 | ELECTRIC - FINAL | IVR USER | Approved | IVRS - RI canceled |
| 01/21/2021 | PLUMBING - SEWER HCS CONNECT | DQUINN | Approved | APPROVED OK FROM STREET SADDLE TO HOUSE CLEANOUTS |
| 02/02/2021 | FRAMING | DQUINN | Approved | |
| 02/02/2021 | ROOF NAILING | DQUINN | Approved | |
| 02/02/2021 | EXT METAL CLIPS/EXT SHEATHING | DQUINN | Approved | |
| 02/19/2021 | PLUMBING - GAS PRESSURE TEST | DQUINN | Approved | |
| 02/19/2021 | PLUMBING - YARD WTR LINE/TEST | DQUINN | Approved | |
| 02/19/2021 | PLUMBING - INTERMEDIATE | DQUINN | Approved | |
| 02/19/2021 | RESIDENTIAL INTERMEDIATE | DQUINN | Approved | |
| 03/05/2021 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | |
| 03/19/2021 | TEP CLEARANCE - PM | DQUINN | Approved | CODE ECO |
| 03/19/2021 | ELECTRIC - CONSTRUCTION POWER | DQUINN | Approved | |
| 06/28/2021 | OUTDOOR LIGHTING FINAL | DQUINN | Approved | |
| 06/28/2021 | BUILDING - FINAL | DQUINN | Approved | |
| 06/28/2021 | MECHANICAL - FINAL | DQUINN | Approved | |
| 06/28/2021 | PLUMBING - FINAL | DQUINN | Approved | |
| 06/28/2021 | ELECTRIC - SERVICE UPGRADE | DQUINN | Approved |