Permit: T19CM09250
Permit Details
Apply Date:
12/17/2019
Applicant:
N/A
Description:
SFR ADDITION & REMODEL: 3BDR & BATH AND GARAGE
Contractors:
- DEL BAC BUILDING CONTRACTOR INC
Permit Reviews
Permit Number - T19CM09250
Permit Status: Final
Permit Description: SFR ADDITION & REMODEL: 3BDR & BATH AND GARAGE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/02/2020 | RESUBMITTAL | 04/17/2020 | COMPLETED |
05/22/2020 | REVISION - - 1ST | 02/24/2021 | COMPLETED |
12/17/2019 | PLANS OK TO SUBMIT - RES | 12/18/2019 | COMPLETED |
12/19/2019 | RESUBMITTAL | 03/20/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM09250
Permit Status: Final
Permit Description: SFR ADDITION & REMODEL: 3BDR & BATH AND GARAGE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
12/17/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T19CM09250
Permit Description: SFR ADDITION & REMODEL: 3BDR & BATH AND GARAGE
Total Completed Inspections - 21
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/02/2020 | PLUMBING - ROUGH, SOIL | TVALENCIA | Approved | |
06/10/2020 | TEP CLEARANCE - PM | TTREMBULAK | Approved | CODE TMPP |
06/10/2020 | ELECTRIC - CONSTRUCTION POWER | TTREMBULAK | Approved | Clearance for TEP TMPP called in to Natalie at 11:25 |
07/17/2020 | BUILDING PRE-SLAB | TTREMBULAK | Approved | Approved |
08/20/2020 | ROOF NAILING | TTREMBULAK | Approved | Approved |
08/20/2020 | EXT METAL CLIPS/EXT SHEATHING | TTREMBULAK | Approved | Approved |
11/20/2020 | GAS CLEARANCE | DQUINN | Approved | CODE |
11/20/2020 | PLUMBING - GAS PRESSURE TEST | DQUINN | Approved | Clear gas |
11/20/2020 | RESIDENTIAL INTERMEDIATE | DQUINN | Approved | |
11/20/2020 | FRAMING | DQUINN | Approved | |
12/28/2020 | MECHANICAL - INTERMEDIATE | TTREMBULAK | Approved | APPROVED |
12/28/2020 | ELECTRIC - UFER | TTREMBULAK | Approved | APPROVED |
12/28/2020 | EXCAVATION/LAYOUT REBAR & ZON | TTREMBULAK | Approved | APPROVED |
12/28/2020 | SHEET ROCK NAILING | TTREMBULAK | Approved | APPROVED |
01/19/2021 | ELECTRIC - UNDERGROUND | ESTEVENS | Approved | APPROVED |
08/03/2021 | ELECTRIC - FINAL | DQUINN | Approved | Ap |
08/03/2021 | OUTDOOR LIGHTING FINAL | DQUINN | Approved | Ap |
08/03/2021 | PLUMBING - FINAL | DQUINN | Approved | Ap |
08/03/2021 | MECHANICAL - FINAL | DQUINN | Approved | Ap 1. Install water heater flue. 2. Install C O detector inside garage pedestrian door in house. 3. Check with security company re heat from equipment above shelf. 4. Move all closet lights that are within 12” of shelving. |
08/06/2021 | PLUMBING - INTERMEDIATE | RELEFANTE | Approved | 3090 |
08/06/2021 | BUILDING - FINAL | RELEFANTE | Approved | AP Clear gas meter release |