Permit: T19CM08782
Permit Details
Apply Date:
11/27/2019
Applicant:
Amaris Grimme
Description:
NEW WATER WELL SITE
Permit Reviews
Permit Number - T19CM08782
Permit Status: Complete
Permit Description: NEW WATER WELL SITE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/15/2020 | RESUBMITTAL | 08/06/2020 | COMPLETED |
| 11/27/2019 | COMMERCIAL - TI | 12/02/2019 | COMPLETED |
| 12/02/2019 | COMMERCIAL - TI | 04/15/2020 | COMPLETED |
Conditions
Permit Number - T19CM08782
Permit Status: Complete
Permit Description: NEW WATER WELL SITE
| Date | Description | Comments |
|---|---|---|
| 11/27/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T19CM08782
Permite Description: NEW WATER WELL SITE
Total Outstanding Inspections - 4
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2022 | COT - LCME - Mechanical Intermediate | N/A | Not Ready | |
| 10/26/2022 | COT - LCME - Mechanical Final | N/A | Not Ready | |
| 12/20/2023 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
| 12/20/2023 | BULD - Electrical Clearance | N/A | Not Applicable |
Completed Inspections
Permit Status: Complete
Permit Number: T19CM08782
Permit Description: NEW WATER WELL SITE
Total Completed Inspections - 12
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/18/2020 | COT - LCEL - Electrical Progress | Passed | {Activity date: 08/18/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by JSCHNEI2 - Approved, Conduits and Boxes installed in CMU wall for Control room.} | |
| 11/20/2020 | COT - LCEL - Grounding/Bonding | Passed | {Activity date: 11/20/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by PAHUMAD1 - Approved, UFFER attached to duct bank from Transformer and SES.} ; {Activity date: 07/17/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved, GEC connection for Equipment ok for concrete encasement. } ; {Activity date: 07/09/2020; Status: Partial Approval; Inspector: TVALENCIA; Comment: Entered by RSALDAT1 - partial 1- Grid grounding system at control room okay.} |
|
| 12/09/2020 | COT - LCEL - Electrical Underground | Passed | {Activity date: 12/09/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by PAHUMAD1 - Approved, underground conduit for Intrusion Switch ok to backfill.} ; {Activity date: 11/20/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by PAHUMAD1 - Approved, Secondary conduits from New transformer and SES Installed through Duct bank and ok for concrete. } ; {Activity date: 07/17/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved, Continuation of Conduits from control room through Re-enforced Duct bank, to Pump and a Well ok for concrete placement.} ; {Activity date: 07/09/2020; Status: Partial Approval; Inspector: TVALENCIA; Comment: Entered by RSALDAT1 - partial 1- Underground conduits for the Gate duct bank and Control Room is okay to cover.} |
|
| 12/22/2020 | COT - LCBU - Preslab | Passed | {Activity date: 12/22/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved, Footing for CMU ok for concrete placem} ; {Activity date: 10/02/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by JSCHNEI2 - Approved, Footing for rolling gate ok for concrete placement } |
|
| 02/17/2021 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 02/17/2021; Status: Approved; Inspector: KCOCO; Comment: Entered by VLEON1 - CODE ECO} | |
| 02/17/2021 | COT - LCEL - Service Upgrade | Passed | {Activity date: 02/17/2021; Status: Approved; Inspector: KCOCO; Comment: Entered by VLEON1 - } | |
| 12/06/2022 | COT - LCME - Mechanical Intermediate | Passed | ||
| 12/06/2022 | COT - LCME - Mechanical Final | Passed | ||
| 12/06/2022 | COT - FCON - Fire - Final | Passed | ||
| 05/25/2023 | ENGR Engineering Final | Passed | ||
| 07/20/2023 | COT - LCEL - Electrical Final | Passed | ||
| 12/20/2023 | COT - HCBU - Building Final | Passed |