Inspection Status: Passed
Inspection History: COT - LCEL - Electrical Underground
| Date |
Description |
Inspector |
Results |
Comments |
| 12/09/2020 |
COT - LCEL - Electrical Underground |
DMUNIZ |
Approved |
Entered by PAHUMAD1 - Approved, underground conduit for Intrusion Switch ok to backfill. |
| 11/20/2020 |
COT - LCEL - Electrical Underground |
DMUNIZ |
Approved |
Entered by PAHUMAD1 - Approved, Secondary conduits from New transformer and SES Installed through Duct bank and ok for concrete.
|
| 07/17/2020 |
COT - LCEL - Electrical Underground |
DMUNIZ |
Approved |
Entered by RSALDAT1 - Approved, Continuation of Conduits from control room through Re-enforced Duct bank, to Pump and a Well ok for concrete placement. |
| 07/09/2020 |
COT - LCEL - Electrical Underground |
TVALENCIA |
Partial Approval |
Entered by RSALDAT1 - partial
1- Underground conduits for the Gate duct bank and Control Room is okay to cover. |