Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T19CM08190
Permit Details
Apply Date:
11/05/2019
Applicant:
SCOTT MARTINEZ
Description:
E - NEW SPLASH PAD AND ASSOCIATED INFRASTRUCTURE
Contractors:
- KAPP CON INCORPORATED
Permit Reviews
Permit Number - T19CM08190
Permit Status: Final
Permit Description: E - NEW SPLASH PAD AND ASSOCIATED INFRASTRUCTURE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/09/2020 | RESUBMITTAL | 04/16/2020 | COMPLETED |
05/13/2020 | REVISION - - 1ST | 06/05/2020 | COMPLETED |
06/05/2020 | REVISION - - 1ST | 09/03/2020 | COMPLETED |
09/03/2020 | REVISION - - 1ST | 10/06/2020 | COMPLETED |
11/05/2019 | COMMERCIAL - NEW | 01/09/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM08190
Permit Status: Final
Permit Description: E - NEW SPLASH PAD AND ASSOCIATED INFRASTRUCTURE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
11/05/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T19CM08190
Permit Description: E - NEW SPLASH PAD AND ASSOCIATED INFRASTRUCTURE
Total Completed Inspections - 17
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/13/2020 | EXCAVATION/LAYOUT REBAR & ZON | WGALLAGHER | Approved | |
05/28/2020 | POOL/SPA BONDING GRID | WGALLAGHER | Approved | |
05/28/2020 | REINFORCED MASONRY PRE-GROUT | WGALLAGHER | Approved | Ok to pour retaining wall (formed wall) |
06/29/2020 | ELECTRIC - UFER | WGALLAGHER | Approved | Approved |
08/03/2020 | BUILDING PRE-SLAB | TTREMBULAK | Approved | Approved |
10/21/2020 | ELECTRIC - OUTDOOR LIGHTING | WGALLAGHER | Approved | |
10/21/2020 | ELECTRIC - PROGRESS | WGALLAGHER | Approved | |
10/21/2020 | ELECTRIC - UNDERGROUND | WGALLAGHER | Approved | |
10/21/2020 | PLUMBING - INTERMEDIATE | WGALLAGHER | Approved | |
10/21/2020 | FRAMING | WGALLAGHER | Approved | |
10/21/2020 | PLUMBING - FINAL | WGALLAGHER | Approved | |
11/02/2020 | ELECTRIC - INTERMEDIATE | TTREMBULAK | Approved | |
11/02/2020 | PLUMBING - YARD WTR LINE/TEST | TTREMBULAK | Approved | Not applicable. |
11/02/2020 | OUTDOOR LIGHTING FINAL | TTREMBULAK | Approved | Not applicable. |
11/02/2020 | ELECTRIC - FINAL | TTREMBULAK | Approved | Approved |
11/02/2020 | BUILDING - FINAL | TTREMBULAK | Approved | Approved, pending engineering and health inspections. |
11/04/2020 | ENGINEERING - FINAL | RLEDONNE | Approved | Approved |