Permit: T19CM07991
Permit Details
Apply Date:
10/29/2019
Applicant:
N/A
Description:
NEW DUPLEX
Contractors:
- MOLINA'S CONSTRUCTION LLC
Permit Reviews
Permit Number - T19CM07991
Permit Status: C of o
Permit Description: NEW DUPLEX
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/14/2020 | RESUBMITTAL | 01/14/2020 | COMPLETED |
| 01/14/2020 | OTHER | 01/22/2020 | COMPLETED |
| 10/30/2019 | PLANS OK TO SUBMIT - RES | 10/30/2019 | COMPLETED |
| 10/30/2019 | RESIDENTIAL - BLDG/WWM | 01/14/2020 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T19CM07991
Permit Description: NEW DUPLEX
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/25/2019 | ROOF NAILING | KEN | Approved | ROOF TRUSSES MUST BE APPROVED PRIOR TO INSPECTION |
| 02/03/2020 | PLUMBING - ROUGH, SOIL | BSTEVENS | Approved | RVI |
| 02/04/2020 | ELECTRIC - UFER | BSTEVENS | Approved | RVI |
| 02/04/2020 | BUILDING PRE-SLAB | BSTEVENS | Approved | RVI |
| 02/04/2020 | EXCAVATION/LAYOUT REBAR & ZON | BSTEVENS | Approved | RVI |
| 10/26/2020 | TEP CLEARANCE - PM | JBURGE | Approved | CODE TMPP |
| 10/26/2020 | ELECTRIC - CONSTRUCTION POWER | JBURGE | Approved | Approved Clearance; Code. TMPP. Ok for construction power. |
| 10/26/2020 | EXT METAL CLIPS/EXT SHEATHING | JBURGE | Approved | Approved |
| 10/26/2020 | FRAMING | JBURGE | Approved | Approved |
| 10/26/2020 | FIREWALL/FIREBARRIER/FIRESTOP | JBURGE | Approved | Approved |
| 10/26/2020 | RESIDENTIAL INTERMEDIATE | JBURGE | Approved | Approved |
| 10/26/2020 | PLUMBING - INTERMEDIATE | JBURGE | Approved | Approved |
| 10/26/2020 | PLUMBING - SEWER HCS CONNECT | JBURGE | Approved | Approved |
| 10/26/2020 | MECHANICAL - INTERMEDIATE | JBURGE | Approved | Approved |
| 10/15/2021 | OUTDOOR LIGHTING FINAL | TGAUSP | Approved | 2090.Approved |
| 10/15/2021 | PLUMBING - FINAL | TGAUSP | Approved | NR |
| 10/15/2021 | BUILDING - FINAL | TGAUSP | Approved | Partial for unit #1 |
| 10/15/2021 | MECHANICAL - FINAL | TGAUSP | Approved | Partial for unit #1 |
| 10/15/2021 | ELECTRIC - FINAL | TGAUSP | Approved | - Partial, for unit #1 |
| 06/01/2022 | PLUMBING - YARD WTR LINE/TEST | TGAUSP | Approved | 3090.Approved |