Permit: T19CM07524
Permit Details
Apply Date:
10/11/2019
Applicant:
N/A
Description:
NEW 14-UNIT MULTI-FAMILY DEVELOPMENT
Contractors:
- CANYON BUILDING AND DESIGN LLC *APA*
Permit Reviews
Permit Number - T19CM07524
Permit Status: C of o
Permit Description: NEW 14-UNIT MULTI-FAMILY DEVELOPMENT
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/21/2020 | RESUBMITTAL | 01/30/2020 | COMPLETED |
09/02/2020 | REVISION - - 1ST | 09/17/2020 | COMPLETED |
10/11/2019 | PLANS OK TO SUBMIT - COMM | 11/07/2019 | COMPLETED |
10/30/2019 | COMMERCIAL - NEW | 12/02/2019 | COMPLETED |
12/03/2019 | RESUBMITTAL | 01/21/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM07524
Permit Status: C of o
Permit Description: NEW 14-UNIT MULTI-FAMILY DEVELOPMENT
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
10/11/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T19CM07524
Permit Description: NEW 14-UNIT MULTI-FAMILY DEVELOPMENT
Total Completed Inspections - 37
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/29/2020 | PLUMBING - ROUGH, SOIL | WGALLAGHER | Approved | Partial approval West building only ok to cover |
07/31/2020 | PLUMBING - PRE SLAB | TTREMBULAK | Approved | Approved |
08/07/2020 | TEP CLEARANCE - PM | ESTEVENS | Approved | CODE TMPP |
08/07/2020 | ELECTRIC - CONSTRUCTION POWER | ESTEVENS | Approved | Approved. The TEP clearance code is TMPP. |
08/11/2020 | ELECTRIC - UFER | ESTEVENS | Approved | Both are approved. |
08/11/2020 | BUILDING PRE-SLAB | ESTEVENS | Approved | Both are approved. |
08/26/2020 | EXCAVATION/LAYOUT REBAR & ZON | ESTEVENS | Approved | Partial. Site wall. From Northwest corner to southwest corner to due East to existing site wall. |
08/28/2020 | SITE - SEWER | ESTEVENS | Approved | Partial. From street manhole, 8 inch line to private manhole. From private manhole, two 4 inch lines to each building. Ok for depth, not under test. |
09/04/2020 | PLUMBING - YARD WTR LINE/TEST | ESTEVENS | Approved | Partial. From both buildings to the property line. |
09/18/2020 | EXT METAL CLIPS/EXT SHEATHING | DQUINN | Approved | Ap Bldg 1 |
09/30/2020 | ELECTRIC - INTERMEDIATE | ESTEVENS | Approved | Approved. Units 1101, 1102, 1103, 1104, 1105. |
10/01/2020 | ROOF NAILING | ENEWCOMB | Approved | |
10/19/2020 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | Frame in all units of bldg 1, ok to cover. All demising walls 5/8 rock ok to tape and fire caulk on 1 side only. 4 light pole footings and ufers ok to pour. |
10/19/2020 | PLUMBING - INTERMEDIATE | DQUINN | Approved | |
10/19/2020 | ELECTRIC - ABOVE CEILING | DQUINN | Approved | Frame in all units of bldg 1, ok to cover. All demising walls 5/8 rock ok to tape and fire caulk on 1 side only. 4 light pole footings and ufers ok to pour. |
10/19/2020 | ELECTRIC - UNDERGROUND | DQUINN | Approved | Frame in all units of bldg 1, ok to cover. All demising walls 5/8 rock ok to tape and fire caulk on 1 side only. 4 light pole footings and ufers ok to pour. |
10/19/2020 | BUILDING ABOVE CEILING | DQUINN | Approved | Frame in all units of bldg 1, ok to cover. All demising walls 5/8 rock ok to tape and fire caulk on 1 side only. 4 light pole footings and ufers ok to pour. |
10/19/2020 | FRAMING | DQUINN | Approved | All frame ok to cover except open side of demising walls. Need to inspect 5/8 x nailing and final fire caulk. |
10/28/2020 | MECHANICAL - ABOVE CEILING | DQUINN | Approved | Ap |
10/29/2020 | SHEET ROCK NAILING | DQUINN | Approved | Ap |
12/01/2020 | ELECTRIC - PROGRESS | DQUINN | Approved | Underground to main bldg panel and risers and grounding ok to backfill. |
01/20/2021 | PLUMBING - FINAL | DQUINN | Approved | APPROVED |
01/20/2021 | MECHANICAL - FINAL | DQUINN | Approved | APPROVED |
01/20/2021 | ELECTRIC - FINAL | DQUINN | Approved | APPROVED |
01/20/2021 | OUTDOOR LIGHTING FINAL | DQUINN | Approved | APPROVED |
01/20/2021 | ELECTRIC - OUTDOOR LIGHTING | DQUINN | Approved | APPROVED |
01/20/2021 | U VALUE FOR WINDOW | DQUINN | Approved | APPROVED |
01/20/2021 | FIRE - ALARM FINAL | wmotto1 | Approved | |
01/28/2021 | STUCCO MESH | DQUINN | Approved | APPROVED |
01/28/2021 | FIRE - FINAL | CBASALDUA | Approved | |
01/28/2021 | FIRE SPKLR - FINAL | CBASALDUA | Approved | |
02/02/2021 | BUILDING - FINAL | JG3 | Approved | |
02/02/2021 | BUILDING - PROGRESS | JG3 | Approved | |
02/02/2021 | PLUMBING - ABOVE CEILING | JG3 | Approved | |
02/02/2021 | PLUMBING - SEWER HCS CONNECT | JG3 | Approved | |
02/02/2021 | PLUMBING - PROGRESS | JG3 | Approved | |
02/02/2021 | MECHANICAL - PROGRESS | JG3 | Approved |