Permit: T19CM05838
Permit Details
Apply Date:
08/15/2019
Applicant:
GRACE SCHAU
Description:
FOUNDATION ONLY
Contractors:
- CHASSE BUILDING TEAM INC
Permit Reviews
Permit Number - T19CM05838
Permit Status: L of c
Permit Description: FOUNDATION ONLY
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/10/2021 | 3RD PARTY REVIEW - REVISION/OTHER | 04/27/2021 | COMPLETED |
08/15/2019 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 09/17/2019 | COMPLETED |
09/17/2019 | POST 3RD PARTY REVIEW | 09/17/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM05838
Permit Status: L of c
Permit Description: FOUNDATION ONLY
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
08/15/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T19CM05838
Permit Description: FOUNDATION ONLY
Total Completed Inspections - 18
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/10/2019 | PLUMBING - PRE SLAB | ESTEVENS | Approved | not complete. |
12/19/2019 | STEM WALL/RETAINING WALL | BSTEVENS | Approved | RVI - 4' HIGH WALL ON GL5 FROM B TO A OK TO POUR |
12/20/2019 | REINFORCED MASONRY PRE-GROUT | DQUINN | Approved | GL c2 at gl 4 to 5.2 Gl 5 at gl c Gl d at 3.5 Gl d.5 at gl 4 Gl f1 to 3.75 to gl2 Gl 4.1 from d3 to f |
12/31/2019 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | |
12/31/2019 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | GL A - B and 5 to 2.8 F-2 footings ok to pour with mud check in footings on thurs morning. |
04/05/2021 | ELECTRIC - UNDERGROUND | RCHANDLER | Approved | |
04/05/2021 | ELECTRIC - UFER | RCHANDLER | Approved | |
05/06/2021 | TEP CLEARANCE - PM | RCHANDLER | Approved | CODE ECO/ UNITS 336, 432, 632. |
07/21/2021 | ELECTRIC - FINAL | RCHANDLER | Approved | NA |
07/21/2021 | BUILDING - FINAL | RCHANDLER | Approved | -AP. Pending SI approval. |
07/21/2021 | FRAMING | RCHANDLER | Approved | NA |
07/21/2021 | PLUMBING - FINAL | RCHANDLER | Approved | NA |
07/21/2021 | BUILDING PRE-SLAB | RCHANDLER | Approved | AP |
02/18/2022 | NPPO - FINAL | DROBERTS | Approved | APPROVED |
02/18/2022 | SIGN - FINAL | DROBERTS | Approved | APPROVED |
02/18/2022 | LANDSCAPE - FINAL | DROBERTS | Approved | APPROVED |
02/18/2022 | ENGINEERING - FINAL | DROBERTS | Approved | APPROVED |
02/18/2022 | RIGHT OF WAY - FINAL | Bravin | Approved | No ROW issues |