Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Permit: T19CM05838

Parcel: 11705033A


Addresses:

340 E 6TH ST

Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Date Description Inspector Results Comments
07/21/2021 EXCAVATION/LAYOUT REBAR & ZON Approved AP
01/07/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 4" pvc rough from D to B.2 and 3.2 to 4.1 ok to backfill.
01/03/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GL 5.2 to 3
A to B
E and W
stairwells of E building ok to 5’ 4”. Ok to grout.
W and N walls 1 to 6.5
And from D to F on gl 1 ok to shoot
01/02/2020 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection
12/31/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GL A - B and 5 to 2.8
F-2 footings ok to pour with mud check in footings on thurs morning.
12/18/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Slab at gl 6.1 to 6.5 and C.3 to D.3 ok to pour.
Gl 5.1 to 6.4 and C.1 to C.4 ok to pour.

Footing gl 5 A to B ok to pour.
12/12/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Stairs 1,2 slabs.
12/03/2019 EXCAVATION/LAYOUT REBAR & ZON Cancelled Called in wrong address.
11/19/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Columns and footings at GL: B.9-F.2/1.8-4.8. Ok to place concrete in progress areas.
11/14/2019 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection Contractor cancelled, will reschedule for 15 November.
11/07/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Pre-slab and May foundation for over head crane as per SSK1.2; 17 October 2019.
11/05/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Concrete shear walls at GL: B.5/6.1. 0k to place concrete in progress areas.
11/04/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CC1 concrete columns; at GL: A.2-D.2/5.4-7.9: 13 columns. Ok to place concrete in progress areas.
10/29/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 5.2 to 8 and a to d4. Elevator pad and columns.
All footings in this grid line section ok to pour.
10/09/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Shotcrete from pier 89, grid line 1J, to Pier 78, 1C. west side of west building.
10/02/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 13 columns from 89-76. Drilling holes, speedy will witness epoxy of rebar to attach ww to for grout placement.
09/30/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval (RVI) CAISONS 69 AND 55 THROUGH 60, 40 THROUGH 45 OK TO POUR
09/27/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval (RVI) CAISONS 61 THROUGH 68 AND 70 THROUGH 77 OK TO POUR
09/26/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CAISONS 78 THROUGH 89 OK TO POUR
09/25/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Pier cages, 75 to 89 ok to drop.
09/24/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Inspect Caissons number 75 to 89.